2501 W CRESTMOORE PL 90065

Certificate Information: 2501 W CRESTMOORE PL 90065

Application / Permit
18014-20000-02320
Plan Check / Job No.
B18VN07261
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'7" X 28'1" ADDITION TO (E) SINGLE FAMILY DWELLING. ADD 2 BEDROOM AND 1 BATHROOM. ALL WORK PER ENGINEER.
Permit Issued
Issued on 9/6/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2018 APPLICANT
Assigned to Plan Check Engineer 5/1/2018 PINANK PATEL
Corrections Issued 5/1/2018 PINANK PATEL
Plan Check Approved 7/22/2019 PINANK PATEL
Issued 9/6/2019 LADBS
CofO in Progress 6/18/2021 HAMIK HARTOUNIAN
Permit Finaled 6/25/2021 DEROLD HAUFF
CofO Issued 6/25/2021 DEROLD HAUFF
Permit Finaled 6/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/1/2018 PINANK PATEL
Eng Process Fee Ord 176,300 Cleared 6/24/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 6/24/2019 CELINA MORENO
Sewer availability Cleared 6/24/2019 CELINA MORENO
Low Impact Development Cleared 6/25/2019 ANDRES COVARRUBIAS
Specific Plan Cleared 7/17/2019 RINA LARA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/4/2019 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/5/2019 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/26/2019 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/3/2019 Approved HAMIK HARTOUNIAN
Underground Mechanical 12/23/2019 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/31/2019 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 12/31/2019 Approved HAMIK HARTOUNIAN
Wood Frame 1/3/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/17/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/27/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 1/27/2020 Approved HAMIK HARTOUNIAN
Insulation 2/10/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/18/2020 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 2/25/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/25/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/4/2020 Approved HAMIK HARTOUNIAN
Insulation 3/4/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 3/31/2020 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/5/2021 Conditional Approval HAMIK HARTOUNIAN
Final 5/5/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/5/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 5/5/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Gas Company HAMIK HARTOUNIAN
Smoke Detectors 5/5/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/17/2021 Approved HAMIK HARTOUNIAN
Final 6/17/2021 OK to Issue CofO HAMIK HARTOUNIAN
Smoke Detectors 6/17/2021 Approved HAMIK HARTOUNIAN