12409 W VAN NUYS BLVD 91331

Certificate Information: 12409 W VAN NUYS BLVD 91331

Application / Permit
18014-20000-02308
Plan Check / Job No.
B18VN07235
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-0" x 20'-0" DET. GARAGE AND ADD 24'7" X 20'2" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 12/4/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2018 APPLICANT
Assigned to Plan Check Engineer 6/7/2018 MENA WASSEF
Corrections Issued 6/7/2018 MENA WASSEF
Applicant returned to address corrections 10/19/2018 JOHNNY WU
Plan Check Approved 11/20/2018 PINANK PATEL
Issued 12/4/2018 LADBS
CofO in Progress 12/31/2019 MICHEL ABAJAN
No Progress 2/18/2020 MICHEL ABAJAN
CofO in Progress 2/21/2020 MICHEL ABAJAN
Permit Finaled 3/9/2020 MICHAEL SMITH
CofO Issued 3/9/2020 MICHAEL SMITH
Permit Finaled 3/9/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/19/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 10/19/2018 JOHN LIN
Roof/Waste drainage to street Cleared 10/19/2018 JOHN LIN
Sewer availability Cleared 10/19/2018 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Munroe,, Massie; Lic. No.: C59905 PO BOX 189      LA CANADA FLINTRIDGE, CA 91012

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/27/2019 Conditional Approval COREY HUPP
Footing/Foundation/Slab 3/14/2019 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2019 Partial Approval MICHEL ABAJAN
Green Building Rough 4/1/2019 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 4/16/2019 Corrections Issued MICHEL ABAJAN
Green Building Rough 4/16/2019 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/19/2019 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/19/2019 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2019 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/23/2019 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 4/29/2019 No Access for Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/1/2019 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 5/3/2019 Approved MICHEL ABAJAN
Green Building Rough 5/3/2019 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/7/2019 Approved MICHEL ABAJAN
HVAC-Rough 5/7/2019 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/7/2019 Approved MICHEL ABAJAN
PLUMBING-Rough 5/7/2019 Not Ready for Inspection MICHEL ABAJAN
Insulation 5/13/2019 Approved MICHEL ABAJAN
Drywall Nailing 5/20/2019 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 5/24/2019 Approved MICHEL ABAJAN
Underground Mechanical 7/18/2019 Corrections Issued MICHEL ABAJAN
Gas Test 8/7/2019 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 8/29/2019 No Access for Inspection MICHEL ABAJAN
Final 8/29/2019 No Access for Inspection MICHEL ABAJAN
Green Building Final 8/29/2019 No Access for Inspection MICHEL ABAJAN
HVAC-Final 8/29/2019 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 8/29/2019 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/29/2019 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 8/29/2019 No Access for Inspection MICHEL ABAJAN
Service/Power Release 9/6/2019 Not Ready for Inspection MARK JOHNSON
Final 9/17/2019 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 9/17/2019 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 12/18/2019 Approved MICHEL ABAJAN
Final 12/18/2019 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 12/18/2019 Approved MICHEL ABAJAN
HVAC-Final 12/18/2019 Approved MICHEL ABAJAN
PLUMBING-Final 12/18/2019 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/18/2019 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/18/2019 Approved MICHEL ABAJAN
Final 12/20/2019 No Access for Inspection MICHEL ABAJAN
Final 12/24/2019 No Access for Inspection MICHEL ABAJAN
Final 12/30/2019 OK to Issue CofO MICHEL ABAJAN