12409 W VAN NUYS BLVD 91331
Certificate Information: 12409 W VAN NUYS BLVD 91331
- Application / Permit
- 18014-20000-02308
- Plan Check / Job No.
- B18VN07235
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" x 20'-0" DET. GARAGE AND ADD 24'7" X 20'2" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 12/4/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | MENA WASSEF |
| Corrections Issued | 6/7/2018 | MENA WASSEF |
| Applicant returned to address corrections | 10/19/2018 | JOHNNY WU |
| Plan Check Approved | 11/20/2018 | PINANK PATEL |
| Issued | 12/4/2018 | LADBS |
| CofO in Progress | 12/31/2019 | MICHEL ABAJAN |
| No Progress | 2/18/2020 | MICHEL ABAJAN |
| CofO in Progress | 2/21/2020 | MICHEL ABAJAN |
| Permit Finaled | 3/9/2020 | MICHAEL SMITH |
| CofO Issued | 3/9/2020 | MICHAEL SMITH |
| Permit Finaled | 3/9/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2018 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2018 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 10/19/2018 | JOHN LIN |
| Sewer availability | Cleared | 10/19/2018 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Munroe,, Massie; Lic. No.: C59905 | PO BOX 189 LA CANADA FLINTRIDGE, CA 91012 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/27/2019 | Conditional Approval | COREY HUPP |
| Footing/Foundation/Slab | 3/14/2019 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2019 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/1/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/16/2019 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 4/16/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2019 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/19/2019 | No Access for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/23/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 4/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/3/2019 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/3/2019 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/7/2019 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/7/2019 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/7/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/7/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 5/13/2019 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/20/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Drywall Nailing | 5/24/2019 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 7/18/2019 | Corrections Issued | MICHEL ABAJAN |
| Gas Test | 8/7/2019 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| Final | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2019 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 8/29/2019 | No Access for Inspection | MICHEL ABAJAN |
| Service/Power Release | 9/6/2019 | Not Ready for Inspection | MARK JOHNSON |
| Final | 9/17/2019 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 9/17/2019 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/18/2019 | Approved | MICHEL ABAJAN |
| Final | 12/18/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 12/18/2019 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/18/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/18/2019 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/18/2019 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/18/2019 | Approved | MICHEL ABAJAN |
| Final | 12/20/2019 | No Access for Inspection | MICHEL ABAJAN |
| Final | 12/24/2019 | No Access for Inspection | MICHEL ABAJAN |
| Final | 12/30/2019 | OK to Issue CofO | MICHEL ABAJAN |