13668 W BAYLISS ROAD 90049

Certificate Information: 13668 W BAYLISS ROAD 90049

Application / Permit
18014-20000-02298
Plan Check / Job No.
B18VN07201
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel kitchen & 2 bathrooms, replace windows and doors on rear side, convert water heater closet to expand walk-in closet, add irregular shape 4.5' x 11.5' to extend foyer and 5.5' x 20.5' for family room expansion. All works are per engineering.
Permit Issued
Issued on 7/25/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2018 APPLICANT
Assigned to Plan Check Engineer 4/30/2018 ALDOUS CHIC
Corrections Issued 4/30/2018 ALDOUS CHIC
Plan Check Approved 7/18/2018 GUANG MIN TUNG
Issued 7/25/2018 LADBS
CofO in Progress 11/21/2019 DAVID FEILER
Permit Finaled 10/21/2021 DANIEL ORRANTE
CofO Issued 10/21/2021 DANIEL ORRANTE
Permit Finaled 10/21/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/30/2018 JOHN LIN
Roof/Waste drainage to street Cleared 4/30/2018 JOHN LIN
Public Works-Highway Ded. Cleared 4/30/2018 JOHN LIN
Public Works-Open Permits Cleared 4/30/2018 JOHN LIN
Public Works-Sewers Cleared 4/30/2018 JOHN LIN
Grading Pre-Inspection Cleared 7/18/2018 ALDOUS CHIC

Contact Information

Contractor Peterbuilt Inc; Lic. No.: 975457-B 7300 HYANNIS DRIVE      WEST HILLS, CA 91307
Engineer Kiledjian, George Zohrab; Lic. No.: C74761 11447 VIKING AVE      NORTHRIDGE, CA 91326

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/22/2018 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 8/23/2018 Approved KENNETH NAGLE
ELECTRICAL-Rough 9/28/2018 Partial Approval KENNETH NAGLE
PLUMBING-Rough 9/28/2018 Partial Approval KENNETH NAGLE
Wood Frame 9/28/2018 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 11/16/2018 Approved KENNETH NAGLE
ELECTRICAL-Rough 11/16/2018 Approved KENNETH NAGLE
Green Building Rough 11/16/2018 Approved KENNETH NAGLE
HVAC-Rough 11/16/2018 Approved KENNETH NAGLE
PLUMBING-Rough 11/16/2018 Approved KENNETH NAGLE
Shower Pan 11/16/2018 Approved KENNETH NAGLE
Interior/Exterior Lathing 12/5/2018 Partial Approval KENNETH NAGLE
Insulation 12/13/2018 Approved KENNETH NAGLE
Interior/Exterior Lathing 12/13/2018 Approved KENNETH NAGLE
Drywall Nailing 12/26/2018 Approved RICHARD STEINBACH
ELECTRICAL-Final 10/18/2019 Approved DAVID FEILER
Final 10/18/2019 Not Ready for Inspection DAVID FEILER
Green Building Final 10/18/2019 Approved DAVID FEILER
PLUMBING-Final 10/18/2019 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/18/2019 SGSOV Approved DAVID FEILER
Smoke Detectors 10/18/2019 Corrections Issued DAVID FEILER
Final 11/12/2019 Partial Inspection DAVID FEILER
Smoke Detectors 11/12/2019 Approved DAVID FEILER
Final 11/20/2019 OK to Issue CofO DAVID FEILER