12941 W OTSEGO ST 91423

Certificate Information: 12941 W OTSEGO ST 91423

Application / Permit
18014-20000-02151
Plan Check / Job No.
B18VN06716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed (13'-10" x 18'-0") addition for (n) kitchen, bathroom & laundry room, (25'-8" x 26'-9") for (n) attached trellis patio. Remodel (e) sfd to enlarge dining room, (n) bathrooms & bedrooms, and convert (3'-9" x 6'-3") & (1'-4" x 4'-0") portion of garage to habitable space per engineering.
Permit Issued
Issued on 12/14/2018
Issuing Office
Valley
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2018 APPLICANT
Green Plans Picked Up 5/14/2018 APPLICANT
Assigned to Plan Check Engineer 5/24/2018 RAPHAEL ROSAS
Corrections Issued 5/31/2018 RAPHAEL ROSAS
Quality Review Completed 6/5/2018 STEVEN KIM
Building Plans Picked Up 6/26/2018 APPLICANT
Applicant returned to address corrections 7/12/2018 RAPHAEL ROSAS
Plan Check Approved 12/14/2018 RAPHAEL ROSAS
Issued 12/14/2018 LADBS
CofO in Progress 1/7/2022 CHRISTOPHE COCHRAN
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 7/12/2018 PARISA ZAHABI
Eng Process Fee Ord 176,300 Cleared 8/9/2018 JOHN LIN
Low Impact Development Cleared 8/9/2018 SAM NAVID
Sewer availability Cleared 8/9/2018 JOHN LIN
Roof/Waste drainage to street Cleared 12/14/2018 MARKOS PEREZ-BRAN

Contact Information

Contractor Poston Development & Construction Co; Lic. No.: 595095-B PO BOX 7391      VAN NUYS, CA 91409
Engineer Nohroodi, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/12/2019 Partial Approval GREG ALLTON
Deputy Drilled-In Anchors 3/19/2019 Conditional Approval GREG ALLTON
Footing/Foundation/Slab 3/22/2019 Partial Approval DOMINIC DANERI
Shower Pan 3/22/2019 Partial Approval DOMINIC DANERI
Floor/Roof Diaphrgm/Shear Wall 4/12/2019 Partial Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 8/8/2019 Partial Approval GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Partial Approval BEAU COLLINS
HVAC-Rough 10/22/2019 Approved BEAU COLLINS
Shower Pan 10/22/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 1/7/2020 Corrections Issued ROBERT MINASSIANS
Green Building Rough 1/7/2020 Not Ready for Inspection ROBERT MINASSIANS
Rough-Elec/Plmb/HVAC 1/7/2020 Corrections Issued ROBERT MINASSIANS
BUILDING-Rough-Frame 1/13/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 1/13/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/13/2020 Approved JENNIFER RABUCHIN
Green Building Rough 1/13/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 1/13/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/15/2020 Partial Approval GREG ALLTON
Insulation 1/15/2020 Approved GREG ALLTON
Drywall Nailing 1/21/2020 Approved GREG ALLTON
Green Building Rough 1/21/2020 Approved GREG ALLTON
Interior/Exterior Lathing 1/21/2020 Partial Approval GREG ALLTON
BUILDING-Rough-Frame 10/4/2021 Approved CHRISTOPHE COCHRAN
Final 10/4/2021 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/4/2021 Approved CHRISTOPHE COCHRAN
Green Building Final 10/4/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 10/4/2021 Approved CHRISTOPHE COCHRAN
Final 11/17/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/17/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Final 1/7/2022 OK to Issue CofO CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/7/2022 SGSOV Approved CHRISTOPHE COCHRAN