1892 N RISING GLEN ROAD 90069

Certificate Information: 1892 N RISING GLEN ROAD 90069

Application / Permit
18014-20000-02088
Plan Check / Job No.
B18VN06532
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
47.26' x 45.45' 1ST, 2ND, AND BASEMENT LEVEL ADDITION TO SINGLE FAMILY DWELLING; INTERIOR REMODEL
Permit Issued
Issued on 10/25/2018
Issuing Office
West Los Angeles
Current Status
Issued on 10/25/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/19/2018 APPLICANT
Green Plans Picked Up 5/1/2018 APPLICANT
Assigned to Plan Check Engineer 5/3/2018 SELLA BENYAMIN
Corrections Issued 5/9/2018 SELLA BENYAMIN
Quality Review Completed 5/10/2018 STEVEN KIM
Building Plans Picked Up 5/11/2018 APPLICANT
Plan Check Approved 9/21/2018 SELLA BENYAMIN
Issued 10/25/2018 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/7/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 6/7/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 6/7/2018 KAYLA PEJI
Miscellaneous Cleared 6/20/2018 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 6/27/2018 JOHN LIN
Roof/Waste drainage to street Cleared 6/27/2018 JOHN LIN
Sewer availability Cleared 6/27/2018 JOHN LIN
Miscellaneous Cleared 7/18/2018 HERMINIGILDO AGUSTIN
Miscellaneous Cleared 7/18/2018 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 8/21/2018 MITESH PATEL
GPI Written Notices Cleared 9/21/2018 SELLA BENYAMIN
Grading Pre-Inspection Cleared 9/21/2018 SELLA BENYAMIN
Green Code Cleared 9/21/2018 DAVID MATSON

Contact Information

Contractor Pacific Cove Development Inc; Lic. No.: 883697-B 1223 WILSHIRE BLVD STE 1570      SANTA MONICA, CA 90403
Engineer Zhuang,, Wenbin; Lic. No.: S5236 184 S ALTADENA DR      PASADENA, CA, CA 91107

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/27/2018 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 1/8/2019 Approved RONALD COWAN
PLUMBING-Rough 2/4/2019 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 4/2/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/4/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 4/8/2019 Conditional Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 7/24/2019 Partial Approval RICHARD STEINBACH
Wood Frame 8/19/2019 Partial Inspection RAUL BARAJAS
Wood Frame 9/24/2019 Not Ready for Inspection ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 9/25/2019 Partial Approval ROBERT CORNELL
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval RAUL BARAJAS
Special/Order Compliance 5/13/2020 Corrections Issued RAUL BARAJAS
Deputy Wood Construction 5/14/2020 Conditional Approval RAUL BARAJAS
Special/Order Compliance 6/12/2020 Corrections Issued BRAD BESCOS
HVAC-Rough 7/22/2020 Corrections Issued RAUL BARAJAS
HVAC-Rough 7/28/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 3/2/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/2/2021 Approved RAUL BARAJAS
Wood Frame 3/2/2021 Not Ready for Inspection RAUL BARAJAS
Deputy Drilled-In Anchors 3/22/2021 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 3/31/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 3/31/2021 Partial Approval RAUL BARAJAS
Green Building Rough 3/31/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Approved RAUL BARAJAS
Insulation 4/28/2021 Approved RAUL BARAJAS
Wood Frame 4/28/2021 Approved RAUL BARAJAS
Drywall Nailing 5/24/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/24/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/21/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/21/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 4/1/2022 Corrections Issued RAUL BARAJAS
PLUMBING-Final 4/1/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 5/18/2022 Corrections Issued RAUL BARAJAS