1892 N RISING GLEN ROAD 90069
Certificate Information: 1892 N RISING GLEN ROAD 90069
- Application / Permit
- 18014-20000-02088
- Plan Check / Job No.
- B18VN06532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 47.26' x 45.45' 1ST, 2ND, AND BASEMENT LEVEL ADDITION TO SINGLE FAMILY DWELLING; INTERIOR REMODEL
- Permit Issued
- Issued on 10/25/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/25/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/19/2018 | APPLICANT |
| Green Plans Picked Up | 5/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2018 | SELLA BENYAMIN |
| Corrections Issued | 5/9/2018 | SELLA BENYAMIN |
| Quality Review Completed | 5/10/2018 | STEVEN KIM |
| Building Plans Picked Up | 5/11/2018 | APPLICANT |
| Plan Check Approved | 9/21/2018 | SELLA BENYAMIN |
| Issued | 10/25/2018 | LADBS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/7/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 6/7/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 6/7/2018 | KAYLA PEJI |
| Miscellaneous | Cleared | 6/20/2018 | DAISY BENICIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2018 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 6/27/2018 | JOHN LIN |
| Sewer availability | Cleared | 6/27/2018 | JOHN LIN |
| Miscellaneous | Cleared | 7/18/2018 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 7/18/2018 | HERMINIGILDO AGUSTIN |
| Low Impact Development | Cleared | 8/21/2018 | MITESH PATEL |
| GPI Written Notices | Cleared | 9/21/2018 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 9/21/2018 | SELLA BENYAMIN |
| Green Code | Cleared | 9/21/2018 | DAVID MATSON |
Contact Information
| Contractor | Pacific Cove Development Inc; Lic. No.: 883697-B | 1223 WILSHIRE BLVD STE 1570 SANTA MONICA, CA 90403 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 184 S ALTADENA DR PASADENA, CA, CA 91107 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/27/2018 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 1/8/2019 | Approved | RONALD COWAN |
| PLUMBING-Rough | 2/4/2019 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 4/2/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/4/2019 | Partial Approval | DANNY TOLENTINO |
| Deputy Reinf. Concrete | 4/8/2019 | Conditional Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 7/24/2019 | Partial Approval | RICHARD STEINBACH |
| Wood Frame | 8/19/2019 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 9/24/2019 | Not Ready for Inspection | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2019 | Partial Approval | ROBERT CORNELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2019 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2020 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Partial Approval | RAUL BARAJAS |
| Special/Order Compliance | 5/13/2020 | Corrections Issued | RAUL BARAJAS |
| Deputy Wood Construction | 5/14/2020 | Conditional Approval | RAUL BARAJAS |
| Special/Order Compliance | 6/12/2020 | Corrections Issued | BRAD BESCOS |
| HVAC-Rough | 7/22/2020 | Corrections Issued | RAUL BARAJAS |
| HVAC-Rough | 7/28/2020 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 3/2/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 3/2/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 3/2/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 3/22/2021 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/31/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/31/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 3/31/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Approved | RAUL BARAJAS |
| Insulation | 4/28/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 4/28/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/24/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/24/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/1/2022 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 4/1/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/18/2022 | Corrections Issued | RAUL BARAJAS |