9664 N LEMONA AVE 91343

Certificate Information: 9664 N LEMONA AVE 91343

Application / Permit
18014-20000-01865
Plan Check / Job No.
B18VN05856
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Expansion of 2nd flr existing storage loft over garage. Conversion and interior remodel of entire 2nd flr into (N) Accessory Dwelling Unit per AB 494 and SB 229. Convert irr. 8'-6" x 31'-1" portion of 1st flr into a recreation room. All work per engineer.
Permit Issued
Issued on 11/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 DAWN MC NULTY
Corrections Issued 4/19/2018 DAWN MC NULTY
Quality Review Completed 4/23/2018 CHON CHIO KUO
Building Plans Picked Up 4/23/2018 APPLICANT
Applicant returned to address corrections 6/5/2018 ARTIN ZARUKIAN
Plan Check Approved 6/3/2019 ANGELICA MARTINEZ
Issued 11/25/2019 LADBS
CofO in Progress 9/26/2020 JENNIFER RABUCHIN
CofO Issued 12/8/2020 MICHAEL SMITH
Permit Finaled 12/8/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/11/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 5/11/2018 JOHN LIN
Sewer availability Cleared 5/11/2018 JOHN LIN
Construction within easement Cleared 11/14/2018 WALTER RAMIREZ

Contact Information

Architect Dell,, Richard Erwin; Lic. No.: C11985 RED ARCHITECTURAL GROUP   3436 N. VERDUGO RD STE 200    GLENDALE, CA 91208
Contractor Owner-Builder       ,
Engineer Schulz,, Les Eric; Lic. No.: S2570 346 N LIMA      SIERRA MADRE, CA 91024

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/13/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/13/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/13/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 2/13/2020 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 2/18/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 2/25/2020 Approved JENNIFER RABUCHIN
Shower Pan 3/10/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/30/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/30/2020 Corrections Issued JENNIFER RABUCHIN
Final 7/30/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/30/2020 Approved JENNIFER RABUCHIN
Green Building Final 7/30/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 7/30/2020 Approved JENNIFER RABUCHIN
HVAC-Final 7/30/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 7/30/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/30/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/30/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/23/2020 Approved JENNIFER RABUCHIN
Final 9/23/2020 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 9/23/2020 Approved JENNIFER RABUCHIN
HVAC-Final 9/23/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/23/2020 Approved JENNIFER RABUCHIN