10530 W OHIO AVE 90024
Certificate Information: 10530 W OHIO AVE 90024
- Application / Permit
- 18014-20000-01828
- Plan Check / Job No.
- B18VN05736
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20' X 14' AND 21'-3" X 17'-6" IRR. ADDITION TO THE EXISTING 1-STORY DWELLING TO REMODEL AND RECONFIGURE ALL ROOMS. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/15/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2018 | SARAH YOUSSEF |
| Corrections Issued | 4/6/2018 | SARAH YOUSSEF |
| Plan Check Approved | 5/11/2018 | ANGELICA MARTINEZ |
| Issued | 5/15/2018 | LADBS |
| CofO in Progress | 6/29/2020 | KENNETH NAGLE |
| Permit Finaled | 6/30/2020 | VINCENT COTTON |
| Permit Finaled | 6/30/2020 | VINCENT COTTON |
| CofO Issued | 6/30/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/4/2018 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2018 | CARLA VALLADARES |
| Roof/Waste drainage to street | Cleared | 5/10/2018 | CARLA VALLADARES |
| Sewer availability | Cleared | 5/10/2018 | CARLA VALLADARES |
| GPI Written Notices | Cleared | 5/11/2018 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 5/11/2018 | SARAH YOUSSEF |
| Metro Rail approval | Cleared | 5/11/2018 | SARAH YOUSSEF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2018 | Corrections Issued | MICHAEL PELHAM |
| Shower Pan | 6/27/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/2/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| METHANE-Barrier | 7/2/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| METHANE-Subgrade | 7/2/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/3/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/3/2018 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/23/2018 | Corrections Issued | MICHAEL PELHAM |
| METHANE-Barrier | 7/23/2018 | Approved | MICHAEL PELHAM |
| METHANE-Subgrade | 7/23/2018 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/24/2018 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/24/2018 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2018 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 9/17/2018 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2018 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 9/20/2018 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2018 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 10/26/2018 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2018 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 11/5/2018 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2018 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 1/22/2019 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 1/25/2019 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/25/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Pre-Inspection | 1/25/2019 | Partial Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 1/30/2019 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/30/2019 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 2/1/2019 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 2/1/2019 | Approved | ANTHONY MCDOWALL |
| METHANE-Rough | 2/1/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Shower Pan | 2/1/2019 | Approved | ANTHONY MCDOWALL |
| Insulation | 2/5/2019 | Approved | DAVID HEINE |
| Drywall Nailing | 2/13/2019 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/13/2019 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/3/2019 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 6/3/2019 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 6/11/2019 | Approved | ROBERT VORHIS |
| Gas Test | 6/11/2019 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 6/11/2019 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 8/9/2019 | Not Ready for Inspection | ROBERT SHELLY |
| HVAC-Final | 8/9/2019 | Not Ready for Inspection | ROBERT SHELLY |
| PLUMBING-Final | 8/9/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Underground Mechanical | 8/9/2019 | Not Ready for Inspection | ROBERT SHELLY |
| ELECTRICAL-Final | 1/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 1/14/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 1/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/18/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 2/18/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 2/18/2020 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 2/18/2020 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 2/18/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 2/18/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 2/26/2020 | Corrections Issued | ROBERT SHELLY |
| Final | 3/3/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 6/29/2020 | Conditional Approval | KENNETH NAGLE |