5694 N COLLINS PL 91367

Certificate Information: 5694 N COLLINS PL 91367

Application / Permit
18014-20000-01784
Plan Check / Job No.
B18VN05574
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 14'x20' TO THE (E) SINGLE FAMILY DWELLING. PER LA STD WFPP.
Permit Issued
Issued on 4/12/2018
Issuing Office
Valley
Current Status
CofO Issued on 8/31/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2018 APPLICANT
Assigned to Plan Check Engineer 4/4/2018 TROY DEGUZMAN
Corrections Issued 4/4/2018 TROY DEGUZMAN
Plan Check Approved 4/11/2018 PINANK PATEL
Issued 4/12/2018 LADBS
CofO in Progress 8/27/2021 HENRY KIM
Permit Finaled 8/31/2021 JOHN JANSON
CofO Issued 8/31/2021 JOHN JANSON
Permit Finaled 8/31/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2018 KAYLA PEJI
Roof/Waste drainage to street Cleared 4/5/2018 KAYLA PEJI
Sewer availability Cleared 4/5/2018 KAYLA PEJI
Grading Pre-Inspection Cleared 4/11/2018 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2020 Approved HENRY KIM
Footing/Foundation/Slab 4/8/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 4/16/2021 Corrections Issued HENRY KIM
Pre-Inspection 4/28/2021 Not Ready for Inspection HENRY KIM
Footing/Foundation/Slab 5/7/2021 Approved HENRY KIM
ELECTRICAL-Rough 6/8/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 6/8/2021 Corrections Issued HENRY KIM
Deputy Wood Construction 6/10/2021 Conditional Approval ASHLEY THOMPSON
ELECTRICAL-Rough 6/14/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 6/14/2021 Corrections Issued HENRY KIM
Sewer 6/14/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Approved HENRY KIM
PLUMBING-Rough 6/18/2021 Approved HENRY KIM
Sewer 6/18/2021 Approved HENRY KIM
BUILDING-Rough-Frame 6/24/2021 Approved HENRY KIM
Green Building Rough 6/24/2021 Approved HENRY KIM
Insulation 6/24/2021 Approved HENRY KIM
Interior/Exterior Lathing 6/24/2021 Approved HENRY KIM
Drywall Nailing 7/2/2021 Corrections Issued SHAVONNE ESPINOZA
Special/Order Compliance 7/2/2021 Approved JEFFREY PARD
Special/Order Compliance 7/3/2021 Approved JEFFREY PARD
Pre-Inspection 7/9/2021 Partial Inspection RYAN SALAZAR
Shower Pan 7/9/2021 Approved RYAN SALAZAR
Drywall Nailing 7/16/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/16/2021 Approved RYAN SALAZAR
Final 7/23/2021 Corrections Issued HENRY KIM
Green Building Final 7/23/2021 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 7/23/2021 Corrections Issued HENRY KIM
ELECTRICAL-Final 8/6/2021 Corrections Issued HENRY KIM
Final 8/6/2021 Corrections Issued HENRY KIM
Green Building Final 8/6/2021 Not Ready for Inspection HENRY KIM
HVAC-Final 8/6/2021 Corrections Issued HENRY KIM
PLUMBING-Final 8/6/2021 Corrections Issued HENRY KIM
Smoke Detectors 8/6/2021 Partial Inspection HENRY KIM
ELECTRICAL-Final 8/23/2021 Corrections Issued HENRY KIM
Final 8/23/2021 Corrections Issued HENRY KIM
Green Building Final 8/23/2021 Approved HENRY KIM
HVAC-Final 8/23/2021 Approved HENRY KIM
PLUMBING-Final 8/23/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Approved HENRY KIM
Smoke Detectors 8/23/2021 Approved HENRY KIM
ELECTRICAL-Final 8/27/2021 Approved HENRY KIM
Final 8/27/2021 OK to Issue CofO HENRY KIM
PLUMBING-Final 8/27/2021 Approved HENRY KIM
Pre-Inspection 8/27/2021 Partial Inspection RYAN SALAZAR