14207 W LEMAY ST 91405

Certificate Information: 14207 W LEMAY ST 91405

Application / Permit
18014-20000-01724
Plan Check / Job No.
B18VN05371
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT AND ADD 16'-11" X 10' 5" TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 1/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2018 APPLICANT
Assigned to Plan Check Engineer 4/2/2018 MENA WASSEF
Corrections Issued 4/2/2018 MENA WASSEF
Plan Check Approved 1/16/2019 GURUNATH NESARAJAH
Issued 1/18/2019 LADBS
CofO in Progress 4/22/2020 MISAEL ESPARZA
CofO in Progress 6/30/2020 MISAEL ESPARZA
CofO Issued 7/1/2020 MICHAEL SMITH
Permit Finaled 7/1/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/4/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 4/4/2018 KAYLA PEJI
Permit Cleared 4/4/2018 KAYLA PEJI
Sewer availability Cleared 4/4/2018 KAYLA PEJI
HPOZ Cleared 1/15/2019 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 1/15/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2019 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 7/24/2019 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 7/29/2019 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/19/2019 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/19/2019 Approved ARAM AVEDISIAN
Green Building Rough 11/19/2019 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/19/2019 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 11/21/2019 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/21/2019 Approved ARAM AVEDISIAN
Underground Mechanical 11/21/2019 Approved ARAM AVEDISIAN
Insulation 11/26/2019 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/26/2019 Partial Approval ARAM AVEDISIAN
Drywall Nailing 12/3/2019 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/3/2019 Partial Approval ARAM AVEDISIAN
Shower Pan 12/3/2019 Approved ARAM AVEDISIAN
Final 1/30/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 1/30/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/30/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 1/30/2020 Corrections Issued MISAEL ESPARZA
Final 2/12/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/12/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/12/2020 Approved MISAEL ESPARZA
Final 4/14/2020 OK to Issue CofO MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/14/2020 SGSOV Approved MISAEL ESPARZA
Special/Order Compliance 4/14/2020 Approved GREGG CUMMINGS