7726-7728 N DUCOR AVE 91304

Certificate Information: 7726-7728 N DUCOR AVE 91304

Application / Permit
18014-20000-01576
Plan Check / Job No.
B18VN04971
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-10" x 21'-9" ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AND 45'-9" x 54'-6" IRRG. ADDITION TO REAR TO EXPAND (E) SFD. ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 MENA WASSEF
Green Plans Picked Up 4/3/2018 APPLICANT
Corrections Issued 4/12/2018 MENA WASSEF
Quality Review Completed 4/24/2018 DOUGLAS NAKATANI
Building Plans Picked Up 4/24/2018 APPLICANT
Plan Check Approved 5/11/2018 MENA WASSEF
Issued 12/9/2021 APPLICANT
Refund in Progress 12/23/2022 TERENCE SHIA
Refund Withdrawn 4/20/2023 AGNES SONDERVAN
Issued 4/20/2023 AGNES SONDERVAN
CofO in Progress 6/15/2023 CHRIS CHRISTENSEN
Permit Finaled 8/23/2023 JOHN JANSON
CofO Issued 8/23/2023 JOHN JANSON
Permit Finaled 8/23/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/24/2018 KENNETH PHAM
Eng Process Fee Ord 176,300 Cleared 4/30/2018 LEE GUILBEAUX
Sewer availability Cleared 4/30/2018 LEE GUILBEAUX
Green Code Cleared 5/1/2018 MICHAEL AYERS
Low Impact Development Cleared 5/11/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 5/11/2018 KAREN LE

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari, Gentjan; Lic. No.: C88031 157 S LOS ROBLES AVE   12    LOS ANGELES, CA 91101

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/10/2022 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 1/11/2022 Approved PETER FOLLING
PLUMBING-Rough 1/19/2022 Approved PETER FOLLING
Sewer 1/19/2022 Approved PETER FOLLING
ELECTRICAL-Rough 1/28/2022 Approved JEFFREY PARD
HVAC-Rough 1/28/2022 Corrections Issued JEFFREY PARD
HVAC-Rough 2/1/2022 Approved PETER FOLLING
Wood Frame 2/1/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/9/2022 Corrections Issued PETER FOLLING
Interior/Exterior Lathing 2/9/2022 Partial Approval PETER FOLLING
Shower Pan 2/9/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 2/15/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 2/15/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 2/24/2022 Approved PETER FOLLING
Interior/Exterior Lathing 2/24/2022 Approved PETER FOLLING
Drywall Nailing 3/11/2022 Approved JAVIER RAMOS JR
Insulation 3/11/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/2/2022 Approved CHRIS CHRISTENSEN
Final 5/2/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/2/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 5/2/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/2/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/2/2022 Approved CHRIS CHRISTENSEN
Final 5/26/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 5/26/2022 Approved CHRIS CHRISTENSEN
Final 6/14/2023 OK to Issue CofO CHRIS CHRISTENSEN