13151 W BRACKEN ST 91331
Certificate Information: 13151 W BRACKEN ST 91331
- Application / Permit
- 18014-20000-01384
- Plan Check / Job No.
- B18VN04371
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 20'3" X18'3" AND CONVERT 20'3" X 18'3" GARAGE TO ACCESSORY DWELLING UNIT PER AB AND SB
- Permit Issued
- Issued on 7/24/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | MICHAEL PEREZ |
| Corrections Issued | 3/22/2018 | MICHAEL PEREZ |
| Plan Check Approved | 8/2/2018 | PINANK PATEL |
| Issued | 7/24/2019 | LADBS |
| CofO in Progress | 12/22/2022 | MICHEL ABAJAN |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2018 | KAYLA PEJI |
| Permit | Cleared | 3/15/2018 | KAYLA PEJI |
| Roof/Waste drainage to street | Cleared | 3/15/2018 | KAYLA PEJI |
| Construction near power lines | Cleared | 7/13/2018 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/13/2018 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2018 | KENNETH PHAM |
| Sewer availability | Cleared | 8/2/2018 | KENNETH PHAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2019 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/13/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/16/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/15/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/15/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 5/15/2020 | Partial Inspection | MICHEL ABAJAN |
| Gas Test | 10/20/2020 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 10/20/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| Insulation | 8/24/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/24/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/13/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/19/2022 | Corrections Issued | MICHEL ABAJAN |
| Final | 7/19/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/19/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 7/19/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/19/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/19/2022 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/19/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/7/2022 | Approved | MICHEL ABAJAN |
| Final | 12/7/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 12/7/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/7/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/7/2022 | Approved | MICHEL ABAJAN |
| Final | 12/22/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 12/22/2022 | Approved | MICHEL ABAJAN |