2403 N GRIFFITH PARK BLVD 90039

Certificate Information: 2403 N GRIFFITH PARK BLVD 90039

Application / Permit
18014-20000-01316
Plan Check / Job No.
B18VN04158
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD IRREGULAR 27'-0" X 40'-3" ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 OVER (E) 2-CAR GARAGE/STORAGE, CONVERT (E) STORAGE AREA TO GARAGE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2018 APPLICANT
Green Plans Picked Up 3/21/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 JENNIFER LEE
Corrections Issued 3/28/2018 JENNIFER LEE
Quality Review Completed 3/28/2018 CHON CHIO KUO
Building Plans Picked Up 4/3/2018 APPLICANT
Applicant returned to address corrections 12/27/2018 JENNIFER LEE
Plan Check Approved 5/21/2019 JENNIFER LEE
Issued 5/21/2019 LADBS
CofO in Progress 5/4/2021 JOSEPH MCGARRY
Permit Finaled 6/3/2021 DEROLD HAUFF
CofO Issued 6/3/2021 DEROLD HAUFF
Permit Finaled 6/3/2021 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 2/28/2019 DAISY BENICIA
Address approval Cleared 2/28/2019 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 2/28/2019 HOWARD COOPER
Green Code Cleared 2/28/2019 PARISA ZAHABI
Sewer availability Cleared 2/28/2019 HOWARD COOPER
Flood clearance Cleared 4/25/2019 HENRY SISOMVANG
Low Impact Development Cleared 5/16/2019 JORGE MEJIA LEMUS
GPI Written Notices Cleared 5/20/2019 JENNIFER LEE
Grading Pre-Inspection Cleared 5/20/2019 JENNIFER LEE
Roof/Waste drainage to street Cleared 5/20/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/16/2019 Corrections Issued BRAD BESCOS
FLOOD-Elevation Certificate 7/16/2019 Conditional Approval BRAD BESCOS
Footing/Foundation/Slab 7/16/2019 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 8/9/2019 Approved BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 8/9/2019 Partial Approval BRAD BESCOS
PLUMBING-Rough 9/10/2019 Corrections Issued BRAD BESCOS
Sewer 9/10/2019 Approved BRAD BESCOS
Underground Mechanical 9/10/2019 Partial Approval BRAD BESCOS
Gas Test 9/19/2019 Not Ready for Inspection BRAD BESCOS
Underground Mechanical 9/19/2019 Partial Approval BRAD BESCOS
HVAC-Rough 10/1/2019 Corrections Issued BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 10/2/2019 Not Ready for Inspection BRAD BESCOS
HVAC-Rough 10/11/2019 Approved BRAD BESCOS
PLUMBING-Rough 10/11/2019 Approved BRAD BESCOS
Underground Mechanical 10/11/2019 Approved BRAD BESCOS
ELECTRICAL-Rough 10/23/2019 Corrections Issued BRAD BESCOS
BUILDING-Rough-Frame 10/28/2019 Corrections Issued BRAD BESCOS
ELECTRICAL-Rough 10/28/2019 Approved BRAD BESCOS
Green Building Rough 10/28/2019 Approved BRAD BESCOS
BUILDING-Rough-Frame 11/13/2019 Partial Approval BRAD BESCOS
Insulation 11/13/2019 Approved BRAD BESCOS
Drywall Nailing 11/25/2019 Approved CHARLES BOGHOSKHAN
Light Gage Steel Frame 12/16/2019 Not Ready for Inspection BRAD BESCOS
Structural Steel Frame 12/16/2019 Not Ready for Inspection BRAD BESCOS
Service/Power Release 2/19/2020 Corrections Issued JOSEPH MCGARRY
Service/Power Release 4/17/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 5/8/2020 Approved JOSEPH MCGARRY
HVAC-Final 5/8/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 5/8/2020 Approved JOSEPH MCGARRY
Shower Pan 6/12/2020 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 8/14/2020 Approved ARTHUR SARGSYAN
Light Gage Steel Frame 8/17/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Structural Steel Frame 8/17/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/11/2020 Approved JOSEPH MCGARRY
Structural Steel Frame 9/11/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/24/2020 Approved JOSEPH MCGARRY
Final 11/24/2020 Corrections Issued JOSEPH MCGARRY
Gas Test 11/24/2020 Approved JOSEPH MCGARRY
Green Building Final 11/24/2020 Approved JOSEPH MCGARRY
HVAC-Final 11/24/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 11/24/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved JOSEPH MCGARRY
Final 4/28/2021 No Access for Inspection HAMIK HARTOUNIAN
Final 4/30/2021 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 4/30/2021 Not Required JOSEPH MCGARRY