12859-12861 W WEIDNER ST 91331

Certificate Information: 12859-12861 W WEIDNER ST 91331

Application / Permit
18014-20000-01224
Plan Check / Job No.
B18VN03861
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remove 14'-5" x 25'-6" convered patio and add 29' x 29'-8" for new bedrooms, bathroom and den to (e) sfd. Remodel (e) sfd to convert bedroom to study. Convert 17' x 25' (e) attached rec room and add 7'-8" x 29' to create (n) accessory dwelling unit per AB 494 & SB 229. All work per engineering.
Permit Issued
Issued on 3/8/2021
Issuing Office
Current Status
Issued on 3/8/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/7/2018 APPLICANT
Assigned to Plan Check Engineer 3/8/2018 ANDRES MATA
Corrections Issued 3/11/2018 ANDRES MATA
Quality Review Completed 3/13/2018 DOUGLAS NAKATANI
Applicant returned to address corrections 4/23/2019 RAPHAEL ROSAS
Plan Check Approved 6/11/2019 ANGELICA MARTINEZ
Issued 3/8/2021 APPLICANT
Building Plans Picked Up 3/11/2021 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/22/2018 RIDWAN HARDY
Address approval Cleared 4/22/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 4/23/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 4/23/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 6/11/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 6/11/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/30/2021 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/18/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/19/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/19/2021 Approved MICHEL ABAJAN
Green Building Rough 8/19/2021 Approved MICHEL ABAJAN
HVAC-Rough 8/19/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 8/19/2021 Approved MICHEL ABAJAN
Insulation 9/1/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/1/2021 Approved MICHEL ABAJAN
Drywall Nailing 9/24/2021 Approved MICHEL ABAJAN
Sewer 11/5/2021 Approved MICHEL ABAJAN
Underground Mechanical 11/5/2021 Approved MICHEL ABAJAN
Final 1/14/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 1/14/2022 Approved MICHEL ABAJAN
Green Building Final 1/14/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/14/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/26/2022 Approved MICHEL ABAJAN
Final 1/26/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 1/26/2022 Approved MICHEL ABAJAN
PLUMBING-Final 1/26/2022 Approved MICHEL ABAJAN