3745 N BERRY DR 91604

Certificate Information: 3745 N BERRY DR 91604

Application / Permit
18014-20000-01211
Plan Check / Job No.
B18VN03831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 22'-0"x 20'-1" 2ND FLOOR ACCESSORY DWELLING UNIT ABOVE (E) ONE STORY GARAGE PER AB 494 AND SB 229.
Permit Issued
Issued on 10/30/2018
Issuing Office
Valley
Current Status
CofO Issued on 12/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2018 APPLICANT
Green Plans Picked Up 3/27/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 TROY DEGUZMAN
Corrections Issued 4/10/2018 TROY DEGUZMAN
Quality Review Completed 4/11/2018 STEVEN KIM
Building Plans Picked Up 4/11/2018 APPLICANT
Applicant returned to address corrections 5/18/2018 TROY DEGUZMAN
Applicant returned to address corrections 8/16/2018 TROY DEGUZMAN
Plan Check Approved 9/18/2018 TROY DEGUZMAN
Issued 10/30/2018 LADBS
CofO in Progress 9/1/2020 ARAM AVEDISIAN
Permit Finaled 12/26/2020 MICHAEL SMITH
CofO Issued 12/26/2020 MICHAEL SMITH
Permit Finaled 12/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/24/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 4/24/2018 KAYLA PEJI
BHO/Hillside ordinance Cleared 4/24/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 4/24/2018 KAYLA PEJI
Hydrant and Access approval Cleared 4/24/2018 JOHN DALLAS
Sewer availability Cleared 4/24/2018 KAYLA PEJI
GPI Written Notices Cleared 5/18/2018 TROY DEGUZMAN
Grading Pre-Inspection Cleared 5/18/2018 TROY DEGUZMAN
Green Code Cleared 5/18/2018 PARISA ZAHABI
Low Impact Development Cleared 6/4/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/5/2018 STEVE MELGAR
Construction near power lines Cleared 7/25/2018 RIDWAN HARDY
Specific Plan Cleared 7/25/2018 ANDRE CALDERON

Contact Information

Contractor Owner-Builder       ,
Engineer Basso, Alexandre; Lic. No.: C77670 3045 COMMUNITY AVENUE      LA CRESCENTA, CA 91214

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2019 Approved RAYMOND KEHOE
Footing/Foundation/Slab 9/18/2019 Partial Approval RAYMOND KEHOE
Footing/Foundation/Slab 10/30/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/6/2019 Partial Approval RAYMOND KEHOE
Deputy Steel/Welding 11/12/2019 Approved RAYMOND KEHOE
Excavation/Setback/Form/Re-Bar 11/12/2019 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 11/22/2019 Partial Approval RAYMOND KEHOE
Deputy Steel/Welding 11/25/2019 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Corrections Issued ROBERT MINASSIANS
Floor/Roof Diaphrgm/Shear Wall 12/19/2019 Partial Approval RAYMOND KEHOE
Special/Order Compliance 1/10/2020 Corrections Issued DANIEL ORRANTE
Special/Order Compliance 1/10/2020 Partial Inspection MICHAEL SMITH
ELECTRICAL-Rough 3/17/2020 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/17/2020 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 3/17/2020 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 3/31/2020 No Access for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Approved ARAM AVEDISIAN
HVAC-Rough 3/31/2020 No Access for Inspection ARAM AVEDISIAN
PLUMBING-Rough 3/31/2020 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 4/3/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/3/2020 Approved ARAM AVEDISIAN
Green Building Rough 4/3/2020 Approved ARAM AVEDISIAN
HVAC-Rough 4/3/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/3/2020 Approved ARAM AVEDISIAN
Special/Order Compliance 4/3/2020 Partial Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 4/3/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/8/2020 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 4/14/2020 Approved JEFFREY PARD
Insulation 4/14/2020 Approved JEFFREY PARD
Special/Order Compliance 4/17/2020 Corrections Issued DANIEL ORRANTE
Special/Order Compliance 4/20/2020 Not Ready for Inspection DANIEL ORRANTE
Drywall Nailing 4/21/2020 Approved DANIEL ORRANTE
Interior/Exterior Lathing 4/21/2020 Approved DANIEL ORRANTE
Interior/Exterior Lathing 4/30/2020 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/4/2020 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 6/4/2020 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 6/4/2020 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 6/15/2020 Not Ready for Inspection ARAM AVEDISIAN
Final 6/15/2020 Corrections Issued ARAM AVEDISIAN
HVAC-Final 6/15/2020 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 6/15/2020 Not Ready for Inspection ARAM AVEDISIAN
Final 8/24/2020 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/24/2020 Approved ARAM AVEDISIAN
Green Building Final 8/24/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/24/2020 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/24/2020 Approved ARAM AVEDISIAN
Structural Steel Frame 8/24/2020 Approved ARAM AVEDISIAN
Final 9/1/2020 OK to Issue CofO ARAM AVEDISIAN