3745 N BERRY DR 91604
Certificate Information: 3745 N BERRY DR 91604
- Application / Permit
- 18014-20000-01211
- Plan Check / Job No.
- B18VN03831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 22'-0"x 20'-1" 2ND FLOOR ACCESSORY DWELLING UNIT ABOVE (E) ONE STORY GARAGE PER AB 494 AND SB 229.
- Permit Issued
- Issued on 10/30/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2018 | APPLICANT |
| Green Plans Picked Up | 3/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2018 | TROY DEGUZMAN |
| Corrections Issued | 4/10/2018 | TROY DEGUZMAN |
| Quality Review Completed | 4/11/2018 | STEVEN KIM |
| Building Plans Picked Up | 4/11/2018 | APPLICANT |
| Applicant returned to address corrections | 5/18/2018 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/16/2018 | TROY DEGUZMAN |
| Plan Check Approved | 9/18/2018 | TROY DEGUZMAN |
| Issued | 10/30/2018 | LADBS |
| CofO in Progress | 9/1/2020 | ARAM AVEDISIAN |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 4/24/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 4/24/2018 | KAYLA PEJI |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2018 | KAYLA PEJI |
| Hydrant and Access approval | Cleared | 4/24/2018 | JOHN DALLAS |
| Sewer availability | Cleared | 4/24/2018 | KAYLA PEJI |
| GPI Written Notices | Cleared | 5/18/2018 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 5/18/2018 | TROY DEGUZMAN |
| Green Code | Cleared | 5/18/2018 | PARISA ZAHABI |
| Low Impact Development | Cleared | 6/4/2018 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 6/5/2018 | STEVE MELGAR |
| Construction near power lines | Cleared | 7/25/2018 | RIDWAN HARDY |
| Specific Plan | Cleared | 7/25/2018 | ANDRE CALDERON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso, Alexandre; Lic. No.: C77670 | 3045 COMMUNITY AVENUE LA CRESCENTA, CA 91214 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/6/2019 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 9/18/2019 | Partial Approval | RAYMOND KEHOE |
| Footing/Foundation/Slab | 10/30/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/6/2019 | Partial Approval | RAYMOND KEHOE |
| Deputy Steel/Welding | 11/12/2019 | Approved | RAYMOND KEHOE |
| Excavation/Setback/Form/Re-Bar | 11/12/2019 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2019 | Partial Approval | RAYMOND KEHOE |
| Deputy Steel/Welding | 11/25/2019 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2019 | Corrections Issued | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2019 | Partial Approval | RAYMOND KEHOE |
| Special/Order Compliance | 1/10/2020 | Corrections Issued | DANIEL ORRANTE |
| Special/Order Compliance | 1/10/2020 | Partial Inspection | MICHAEL SMITH |
| ELECTRICAL-Rough | 3/17/2020 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2020 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 3/17/2020 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/17/2020 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/31/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/31/2020 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/31/2020 | No Access for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/3/2020 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/3/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 4/3/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/3/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/3/2020 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 4/3/2020 | Partial Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/3/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/8/2020 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 4/14/2020 | Approved | JEFFREY PARD |
| Insulation | 4/14/2020 | Approved | JEFFREY PARD |
| Special/Order Compliance | 4/17/2020 | Corrections Issued | DANIEL ORRANTE |
| Special/Order Compliance | 4/20/2020 | Not Ready for Inspection | DANIEL ORRANTE |
| Drywall Nailing | 4/21/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 4/21/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 4/30/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/4/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Final | 6/4/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 6/4/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/15/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 6/15/2020 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 6/15/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 6/15/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/24/2020 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/24/2020 | Approved | ARAM AVEDISIAN |
| Green Building Final | 8/24/2020 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/24/2020 | Approved | ARAM AVEDISIAN |
| Structural Steel Frame | 8/24/2020 | Approved | ARAM AVEDISIAN |
| Final | 9/1/2020 | OK to Issue CofO | ARAM AVEDISIAN |