7522 N BEN AVE 91605
Certificate Information: 7522 N BEN AVE 91605
- Application / Permit
- 18014-20000-01202
- Plan Check / Job No.
- B18VN03803
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-2" X 20' DETACHED GARAGE AND ADD IRREGULAR 25'-0" X 39'-0" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/10/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2018 | JENNIFER LEE |
| Corrections Issued | 3/20/2018 | JENNIFER LEE |
| Applicant returned to address corrections | 5/4/2018 | ANGELICA DAVE |
| Plan Check Approved | 5/7/2018 | SELLA BENYAMIN |
| Issued | 7/10/2018 | LADBS |
| CofO in Progress | 8/24/2022 | JOHN HAYES |
| CofO Issued | 8/24/2022 | MICHAEL SMITH |
| Permit Finaled | 8/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/19/2018 | MITESH PATEL |
| Address approval | Cleared | 4/26/2018 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2018 | KENNETH PHAM |
| Permit | Cleared | 4/26/2018 | KENNETH PHAM |
| Roof/Waste drainage to street | Cleared | 4/26/2018 | KENNETH PHAM |
| Sewer availability | Cleared | 4/26/2018 | KENNETH PHAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/8/2019 | Approved | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 3/27/2019 | Partial Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/25/2019 | No Access for Inspection | WILLIAM KUEHN |
| Underground Mechanical | 4/25/2019 | No Access for Inspection | WILLIAM KUEHN |
| Underground Mechanical | 5/7/2019 | Partial Approval | RAYMOND KEHOE |
| Excavation/Setback/Form/Re-Bar | 5/28/2019 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/28/2019 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 6/5/2019 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/5/2019 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 4/20/2020 | Partial Approval | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 5/6/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 5/6/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Partial Approval | RAYMOND KEHOE |
| Rough-Elec/Plmb/HVAC | 8/7/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Approved | DANIEL DREW |
| Underground Mechanical | 8/7/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | DANIEL DREW |
| Green Building Rough | 9/2/2020 | Approved | DANIEL DREW |
| Insulation | 10/14/2020 | Approved | DANIEL DREW |
| Sewer | 10/19/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 10/28/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/4/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 1/19/2021 | Approved | DAVID MATSON |
| Final | 2/12/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 2/12/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Final | 2/12/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Final | 2/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 2/12/2021 | Approved | DANIEL DREW |
| Final | 6/8/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 6/8/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 6/8/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 6/25/2021 | Approved | DANIEL DREW |
| HVAC-Final | 7/2/2021 | Approved | DANIEL DREW |
| Final | 9/20/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 9/20/2021 | Approved | DANIEL DREW |
| Final | 10/19/2021 | Corrections Issued | DANIEL DREW |
| Final | 7/28/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 8/11/2022 | No Access for Inspection | JOHN HAYES |
| Service/Power Release | 8/11/2022 | No Access for Inspection | JOHN HAYES |
| Final | 8/18/2022 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 8/18/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/23/2022 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 8/23/2022 | Approved | JOHN HAYES |