12842 N SPROULE AVE 91340

Certificate Information: 12842 N SPROULE AVE 91340

Application / Permit
18014-20000-01114
Plan Check / Job No.
B18VN03521
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION & CONVERT (E) DET. GARAGE TO ADU AND STORAGE PER AB 494 AND SB 229
Permit Issued
Issued on 7/23/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2018 APPLICANT
Assigned to Plan Check Engineer 3/1/2018 VLADIMIR ARUTYUNYAN
Corrections Issued 3/7/2018 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 3/9/2018 APPLICANT
Plan Check Approved 7/19/2018 VLADIMIR ARUTYUNYAN
Issued 7/23/2018 LADBS
CofO in Progress 4/5/2021 MISAEL ESPARZA
CofO Issued 7/28/2021 MICHAEL SMITH
Permit Finaled 7/28/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/27/2018 KAYLA PEJI
Eng Process Fee Ord 176,300 Cleared 3/27/2018 KAYLA PEJI
Sewer availability Cleared 3/27/2018 KAYLA PEJI
Low Impact Development Cleared 7/2/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 7/5/2018 JOSEPH RHYU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/1/2019 Approved CHARLES POWELL
BUILDING-Rough-Frame 11/27/2019 Partial Approval CHARLES POWELL
PLUMBING-Rough 11/27/2019 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/29/2019 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/21/2020 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/21/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 2/21/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 2/21/2020 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/27/2020 Approved TROY SANDERS
ELECTRICAL-Rough 3/27/2020 Approved TROY SANDERS
Green Building Rough 3/27/2020 Approved TROY SANDERS
HVAC-Rough 3/27/2020 Approved TROY SANDERS
PLUMBING-Rough 3/27/2020 Approved TROY SANDERS
Insulation 4/3/2020 No Access for Inspection TROY SANDERS
Insulation 4/7/2020 Approved TROY SANDERS
Drywall Nailing 4/16/2020 Approved TROY SANDERS
Interior/Exterior Lathing 4/24/2020 Approved TROY SANDERS
Underground Mechanical 6/19/2020 Approved GREGG CUMMINGS
Service/Power Release 8/12/2020 No Access for Inspection MISAEL ESPARZA
Service/Power Release 8/14/2020 Not Ready for Inspection MISAEL ESPARZA
Gas Test 8/18/2020 Partial Inspection MISAEL ESPARZA
Wood Frame 10/27/2020 Approved MISAEL ESPARZA
Final 2/17/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 2/17/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/17/2021 Corrections Issued MISAEL ESPARZA
Final 3/26/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/26/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 3/26/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/5/2021 Approved MISAEL ESPARZA
Final 4/5/2021 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 4/5/2021 Approved MISAEL ESPARZA
PLUMBING-Final 4/5/2021 Approved MISAEL ESPARZA