15552 W AQUA VERDE DR 90077

Certificate Information: 15552 W AQUA VERDE DR 90077

Application / Permit
18014-20000-00848
Plan Check / Job No.
B18VN02669
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'-4" X 9'-0" ADDITION TO ENLARGE GARAGE. 18'-10" X 48'-6" ADDITION AND REMODEL THROUGHOUT DWELLING FOR NEW STUDY ROOM AND TWO BATHROOMS. ENCLOSE AND CONVERT COVERED PATIO TO ENLARGE KITCHEN.
Permit Issued
Issued on 3/20/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2018 APPLICANT
Assigned to Plan Check Engineer 2/22/2018 JEROME MAGAT PALMA
Corrections Issued 2/26/2018 JEROME MAGAT PALMA
Quality Review Completed 2/27/2018 CHON CHIO KUO
Green Plans Picked Up 2/27/2018 APPLICANT
Building Plans Picked Up 3/6/2018 APPLICANT
Plan Check Approved 3/5/2019 JEROME MAGAT PALMA
Issued 3/20/2019 LADBS
CofO in Progress 5/25/2021 CARLOS MATAMOROS
CofO Issued 6/10/2021 VINCENT COTTON
Permit Finaled 6/10/2021 VINCENT COTTON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/13/2018 CHRISTINE REUSCH
BHO/Hillside ordinance Cleared 3/13/2018 CHRISTINE REUSCH
BHO/Hillside ordinance Cleared 3/13/2018 CHRISTINE REUSCH
Eng Process Fee Ord 176,300 Cleared 3/13/2018 CHRISTINE REUSCH
Sewer availability Cleared 3/13/2018 CHRISTINE REUSCH
Green Code Cleared 3/16/2018 JEROME MAGAT PALMA
GPI Written Notices Cleared 12/20/2018 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 12/20/2018 JEROME MAGAT PALMA
Specific Plan Cleared 2/6/2019 STEVEN WECHSLER
Miscellaneous Cleared 2/26/2019 STEVEN WECHSLER
Low Impact Development Cleared 3/4/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 3/5/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Choe Craig; Lic. No.: 867838-B 3183 WILSHIRE BLVD   196 - E33    LOS ANGELES, CA 90010
Engineer Burnazyan, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 7/3/2019 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 7/16/2019 Corrections Issued DAVID FEILER
Grounding or Bonding 7/16/2019 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/16/2019 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 8/7/2019 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 8/16/2019 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 8/28/2019 Not Ready for Inspection ANTHONY MCDOWALL
Rough-Elec/Plmb/HVAC 8/28/2019 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Conditional Approval ANTHONY MCDOWALL
Deputy Drilled-In Anchors 9/16/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 10/11/2019 Partial Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 11/8/2019 Partial Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 1/17/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 1/17/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 1/28/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval CARLOS MATAMOROS
HVAC-Rough 2/11/2020 Approved CARLOS MATAMOROS
Deputy Wood Construction 3/4/2020 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 3/5/2020 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Approved CARLOS MATAMOROS
Green Building Rough 3/5/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 4/10/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/10/2020 Approved CARLOS MATAMOROS
Green Building Rough 4/10/2020 Approved CARLOS MATAMOROS
Insulation 4/17/2020 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 4/17/2020 Corrections Issued ANTHONY MCDOWALL
Sewer 4/17/2020 Approved ANTHONY MCDOWALL
Drywall Nailing 4/30/2020 Partial Approval CARLOS MATAMOROS
Drywall Nailing 5/6/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/6/2020 Approved CARLOS MATAMOROS
Special/Order Compliance 6/13/2020 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/20/2020 Partial Inspection CHRISTOPHER WILSON
HVAC-Final 7/27/2020 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 8/17/2020 Corrections Issued CARLOS MATAMOROS
Final 8/17/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 8/17/2020 Corrections Issued CARLOS MATAMOROS
Service/Power Release 8/18/2020 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 8/20/2020 Approved CARLOS MATAMOROS
Gas Test 8/20/2020 Approved CARLOS MATAMOROS
PLUMBING-Final 8/20/2020 Approved CARLOS MATAMOROS
Service/Power Release 8/20/2020 Approved CARLOS MATAMOROS
HVAC-Final 8/28/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/11/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 9/17/2020 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 9/17/2020 Approved CARLOS MATAMOROS
Green Building Final 9/17/2020 OK to Expire Permit CARLOS MATAMOROS
HVAC-Final 9/17/2020 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 9/17/2020 Approved CARLOS MATAMOROS
Final 10/7/2020 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 10/7/2020 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Not Ready CARLOS MATAMOROS
Final 3/5/2021 Corrections Issued CARLOS MATAMOROS
Green Building Final 3/5/2021 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Approved CARLOS MATAMOROS
Final 3/15/2021 Partial Approval CARLOS MATAMOROS