Work Description
22'-6" X 24'-1" IRREG SHAPED ADDITION AND REMODEL TO RELOCATE KITCHEN AND BATHROOM. ENLARGE TWO BEDROOMS, ADD NEW LAUNDRY ROOM AND NEW BATHROOM,. ALL WORK PER WFPP.
Permit Issued
Issued on 8/9/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2018 APPLICANT
Assigned to Plan Check Engineer 2/15/2018 JEROME MAGAT PALMA
Corrections Issued 2/15/2018 JEROME MAGAT PALMA
Applicant returned to address corrections 5/29/2018 JEFFREY TANGONAN
Plan Check Approved 5/29/2018 RARES BODEA
Issued 8/9/2018 LADBS
CofO in Progress 2/10/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 5/3/2022 DANIEL ORRANTE
CofO Issued 5/3/2022 DANIEL ORRANTE
Permit Finaled 5/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 4/10/2018 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/17/2018 EDUARDO PEDROZA
Roof/Waste drainage to street Cleared 5/29/2018 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/17/2020 Corrections Issued PIERRE VEGA
BUILDING-Rough-Frame 10/7/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/7/2020 Not Ready for Inspection JOHN HAYES
METHANE-Rough 10/7/2020 Not Ready for Inspection JOHN HAYES
Insulation 10/8/2020 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 10/16/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/19/2020 Approved JOHN HAYES
Green Building Rough 10/19/2020 Approved JOHN HAYES
METHANE-Rough 10/19/2020 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 10/19/2020 Approved JOHN HAYES
Drywall Nailing 11/4/2020 Approved JOHN HAYES
Interior/Exterior Lathing 11/4/2020 Approved JOHN HAYES
Final 12/21/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 12/21/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 12/21/2020 Not Ready for Inspection JOHN HAYES
METHANE-Barrier 12/21/2020 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 12/21/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 12/21/2020 Not Ready for Inspection JOHN HAYES
Final 2/5/2021 No Access for Inspection JOHN HAYES
Footing/Foundation/Slab 2/5/2021 No Access for Inspection JOHN HAYES
Green Building Final 2/5/2021 No Access for Inspection JOHN HAYES
METHANE-Barrier 2/5/2021 No Access for Inspection JOHN HAYES
METHANE-Subgrade 2/5/2021 No Access for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 2/5/2021 No Access for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Corrections Issued JOHN HAYES
Final 8/12/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 8/12/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 8/12/2021 Not Ready for Inspection JOHN HAYES
METHANE-Barrier 8/12/2021 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 8/12/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/12/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 8/12/2021 Not Ready for Inspection JOHN HAYES
Final 2/10/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 2/10/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 2/10/2022 Approved CHRISTOPHER DELLEFIELD
METHANE-Barrier 2/10/2022 Approved CHRISTOPHER DELLEFIELD
METHANE-Subgrade 2/10/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 2/10/2022 Approved CHRISTOPHER DELLEFIELD