6'-6" x 35'-3" ADDITION TO EXPAND (E) BEDROOM AND 7'-1" x 14'-4" TO FRONT TO EXPAND (E) KITCHEN AT FIRST FLOOR AND ENCLOSE 12'-2" x 18'-3" IRRG. OVER IN HEIGHT CEILING TO EXPAND SECOND FLOOR REMODEL SFD. ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 4/18/2018
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2018 APPLICANT
Assigned to Plan Check Engineer 2/8/2018 MENA WASSEF
Corrections Issued 2/16/2018 MENA WASSEF
Quality Review Completed 2/27/2018 DOUGLAS NAKATANI
Building Plans Picked Up 2/27/2018 APPLICANT
Green Plans Picked Up 3/13/2018 APPLICANT
Plan Check Approved 4/10/2018 MENA WASSEF
Issued 4/18/2018 LADBS
CofO in Progress 4/10/2026 DAVID WILLIAMS
CofO Issued 4/11/2026 DEROLD HAUFF
Permit Finaled 4/11/2026 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/13/2018 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 3/13/2018 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 3/13/2018 CHRISTINE REUSCH
Sewer availability Cleared 3/13/2018 CHRISTINE REUSCH
ZA Case Cleared 3/13/2018 ANNA VIDAL
Public Works-Highway Ded. Cleared 3/13/2018 CHRISTINE REUSCH
Public Works-Open Permits Cleared 3/13/2018 CHRISTINE REUSCH
Public Works-Sewers Cleared 3/13/2018 CHRISTINE REUSCH
Green Code Cleared 3/29/2018 MICHAEL AYERS
Specific Plan Cleared 3/29/2018 ANDRE CALDERON
GPI Written Notices Cleared 3/30/2018 MENA WASSEF
Grading Pre-Inspection Cleared 3/30/2018 MENA WASSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/6/2018 Not Ready for Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 6/7/2018 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 6/19/2018 Approved RAUL BARAJAS
PLUMBING-Rough 6/19/2018 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/22/2018 Partial Approval RONALD COWAN
ELECTRICAL-Rough 7/24/2018 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 7/24/2018 Approved RONALD COWAN
HVAC-Rough 7/24/2018 Approved RONALD COWAN
PLUMBING-Rough 7/24/2018 Approved RONALD COWAN
Wood Frame 7/24/2018 Partial Approval RONALD COWAN
Insulation 7/27/2018 Approved RONALD COWAN
Drywall Nailing 8/1/2018 Approved RONALD COWAN
Interior/Exterior Lathing 8/23/2018 Approved RONALD COWAN
BUILDING-Rough-Frame 2/27/2019 Partial Inspection DANNY TOLENTINO
Final 2/27/2019 Partial Inspection DANNY TOLENTINO
Green Building Final 2/27/2019 Not Ready for Inspection DANNY TOLENTINO
Green Building Rough 2/27/2019 Not Ready for Inspection DANNY TOLENTINO
SGSOV-Seismic Gas S/O Valve 2/27/2019 SGSOV Not Ready DANNY TOLENTINO
Smoke Detectors 2/27/2019 Not Ready for Inspection DANNY TOLENTINO
Special/Order Compliance 8/21/2020 Corrections Issued RICHARD STEINBACH
BUILDING-Rough-Frame 3/7/2023 No Access for Inspection RAUL BARAJAS
Final 3/7/2023 No Access for Inspection RAUL BARAJAS
Green Building Final 3/7/2023 No Access for Inspection RAUL BARAJAS
Green Building Rough 3/7/2023 No Access for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 3/7/2023 No Access for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 3/12/2025 Not Ready for Inspection ROY SPAULDING
Final 3/12/2025 Corrections Issued ROY SPAULDING
Green Building Final 3/12/2025 Not Ready for Inspection ROY SPAULDING
Green Building Rough 3/12/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 3/12/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 3/27/2025 Not Ready for Inspection ROY SPAULDING
Final 3/27/2025 Corrections Issued ROY SPAULDING
Green Building Final 3/27/2025 Not Ready for Inspection ROY SPAULDING
Green Building Rough 3/27/2025 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 3/27/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 2/3/2026 Approved ROY SPAULDING
Final 2/3/2026 Corrections Issued ROY SPAULDING
Green Building Final 2/3/2026 Not Ready for Inspection ROY SPAULDING
Green Building Rough 2/3/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 2/3/2026 Approved ROY SPAULDING
ELECTRICAL-Final 4/9/2026 Approved DAVID WILLIAMS
Final 4/9/2026 OK to Issue CofO DAVID WILLIAMS
Green Building Final 4/9/2026 Approved DAVID WILLIAMS
HVAC-Final 4/9/2026 Approved DAVID WILLIAMS
PLUMBING-Final 4/9/2026 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved DAVID WILLIAMS