7811 N ARCOLA AVE 91352
Certificate Information: 7811 N ARCOLA AVE 91352
- Application / Permit
- 18014-20000-00481
- Plan Check / Job No.
- B18VN01521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE EXIST. 18' x 20' DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 & SB 229 AND 8' x 16'ADDITION TO EXPAND THE ACCESSORY DWELLING UNIT PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 09/08/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/13/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2018 | JOSE MENDOZA |
| Corrections Issued | 1/29/2018 | ANDRES MATA |
| Applicant returned to address corrections | 2/1/2018 | MARVEL DELACRUZ |
| Plan Check Approved | 2/8/2018 | ANGELICA MARTINEZ |
| Issued | 2/13/2018 | LADBS |
| CofO in Progress | 11/27/2023 | DAVID ANDERSON |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| CofO Issued | 1/3/2024 | RUBEN SALAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2018 | EDUARDO PEDROZA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2018 | EDUARDO PEDROZA |
| Roof/Waste drainage to street | Cleared | 1/29/2018 | EDUARDO PEDROZA |
| Sewer availability | Cleared | 1/29/2018 | EDUARDO PEDROZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/3/2023 | Approved | THOMAS WOODS |
| Deputy Drilled-In Anchors | 6/5/2023 | Approved | THOMAS WOODS |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | THOMAS WOODS |
| Sewer | 6/12/2023 | Approved | THOMAS WOODS |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/10/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 7/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| MERV13>=Rough | 7/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 7/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/22/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/22/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/22/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/22/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 8/22/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/22/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/25/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/25/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/25/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/25/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 8/29/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/1/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/1/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Gas Test | 10/16/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/16/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 11/2/2023 | Approved | DAVID MATSON |
| Green Building Final | 11/2/2023 | Approved | DAVID MATSON |
| HVAC-Final | 11/2/2023 | Approved | DAVID MATSON |
| MERV13>=Final | 11/2/2023 | Approved | DAVID MATSON |
| PLUMBING-Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Service/Power Release | 11/2/2023 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Verify Rec and Parks Fee Memo | 11/2/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Final | 11/8/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 11/15/2023 | Approved | DAVID ANDERSON |
| Final | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Final | 11/15/2023 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 11/15/2023 | Approved | DAVID ANDERSON |
| Final | 11/21/2023 | OK to Issue CofO | DAVID ANDERSON |
| HVAC-Final | 11/21/2023 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/21/2023 | Approved | DAVID ANDERSON |