6648 W COLGATE AVE 90048
Certificate Information: 6648 W COLGATE AVE 90048
- Application / Permit
- 18014-20000-00177
- Plan Check / Job No.
- B18VN00552
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT AND ADD 2ND FLOOR ADDITION PER AB 494 AND SB 229. ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 11/05/2004. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/4/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | JEFFREY TANGONAN |
| Corrections Issued | 2/21/2018 | JEFFREY TANGONAN |
| Quality Review Completed | 2/23/2018 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 2/28/2018 | APPLICANT |
| Green Plans Picked Up | 2/28/2018 | APPLICANT |
| Applicant returned to address corrections | 11/15/2018 | JEFFREY TANGONAN |
| Plan Check Approved | 11/4/2019 | JEFFREY TANGONAN |
| Issued | 11/4/2019 | LADBS |
| CofO in Progress | 5/3/2021 | ROBERT MINASSIANS |
| CofO in Progress | 5/3/2021 | PATRICK QUALEY |
| CofO Issued | 6/10/2021 | DANIEL SANCHEZ |
| Permit Finaled | 6/10/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2018 | CARLA VALLADARES |
| Roof/Waste drainage to street | Cleared | 3/29/2018 | CARLA VALLADARES |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2018 | DENNIS BRAGIN |
| Sewer availability | Cleared | 4/2/2018 | DENNIS BRAGIN |
| Green Code | Cleared | 10/26/2018 | SARKIS HARABEDIAN |
| ZI | Cleared | 11/14/2018 | SARAH GOLDMAN |
| Construction near power lines | Cleared | 11/1/2019 | OSCAR CASTRO |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 5455 WILSHIRE BLVD #1811 LOS ANGELES, CA 90036 |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2020 | Corrections Issued | PATRICK QUALEY |
| METHANE-Barrier | 3/3/2020 | Not Ready for Inspection | PATRICK QUALEY |
| METHANE-Subgrade | 3/3/2020 | Not Ready for Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 3/5/2020 | Corrections Issued | PATRICK QUALEY |
| METHANE-Barrier | 3/5/2020 | Conditional Approval | PATRICK QUALEY |
| METHANE-Subgrade | 3/5/2020 | Conditional Approval | PATRICK QUALEY |
| Footing/Foundation/Slab | 3/10/2020 | Approved | PATRICK QUALEY |
| METHANE-Barrier | 3/10/2020 | Approved | PATRICK QUALEY |
| METHANE-Subgrade | 3/10/2020 | Approved | PATRICK QUALEY |
| Underground Mechanical | 4/1/2020 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 4/2/2020 | Corrections Issued | PATRICK QUALEY |
| Underground Mechanical | 4/2/2020 | Approved | PATRICK QUALEY |
| Deputy Wood Construction | 5/15/2020 | Approved | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/20/2020 | Corrections Issued | PATRICK QUALEY |
| HVAC-Rough | 5/20/2020 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 5/20/2020 | Corrections Issued | PATRICK QUALEY |
| BUILDING-Rough-Frame | 5/27/2020 | Approved | PATRICK QUALEY |
| ELECTRICAL-Rough | 5/27/2020 | Approved | PATRICK QUALEY |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | PATRICK QUALEY |
| HVAC-Rough | 5/27/2020 | Approved | PATRICK QUALEY |
| METHANE-Rough | 5/27/2020 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 5/27/2020 | Approved | PATRICK QUALEY |
| Sewer | 6/10/2020 | Corrections Issued | PATRICK QUALEY |
| Underground Mechanical | 6/18/2020 | Approved | ARIS ALLAHVERDIAN |
| Drywall Nailing | 7/6/2020 | Approved | ARIS ALLAHVERDIAN |
| Green Building Rough | 7/6/2020 | Approved | ARIS ALLAHVERDIAN |
| Interior/Exterior Lathing | 7/6/2020 | Approved | ARIS ALLAHVERDIAN |
| Interior/Exterior Lathing | 7/16/2020 | Approved | PATRICK QUALEY |
| ELECTRICAL-Final | 12/18/2020 | Approved | PATRICK QUALEY |
| HVAC-Final | 12/18/2020 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 12/18/2020 | Corrections Issued | PATRICK QUALEY |
| Final | 12/22/2020 | Corrections Issued | PATRICK QUALEY |
| Gas Test | 12/22/2020 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 12/22/2020 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 12/22/2020 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2020 | SGSOV Approved | PATRICK QUALEY |
| Service/Power Release | 12/22/2020 | Corrections Issued | PATRICK QUALEY |
| Smoke Detectors | 12/22/2020 | Approved | PATRICK QUALEY |
| Final | 1/7/2021 | Corrections Issued | PATRICK QUALEY |
| Gas Test | 1/7/2021 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 1/7/2021 | Approved | PATRICK QUALEY |
| Service/Power Release | 1/7/2021 | Not Ready for Inspection | PATRICK QUALEY |
| Final | 1/15/2021 | OK to Issue CofO | PATRICK QUALEY |
| Service/Power Release | 1/15/2021 | Approved | PATRICK QUALEY |
| Final | 5/3/2021 | Partial Approval | PATRICK QUALEY |