612 S BROADWAY 90014
Certificate Information: 612 S BROADWAY 90014
- Application / Permit
- 18014-10003-00041
- Plan Check / Job No.
- B18LA18057
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- SUPLEMENTAL TO 18014-10000-00041 TO REVIEW REVISED SHEAR WALL LOCATIONS , CHANGES TO ROOF PENTHOUSE, REVISED STAIR AND ELEVATOR LOCATIONS
- Permit Issued
- Issued on 1/18/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2018 | APPLICANT |
| Green Plans Picked Up | 9/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | LARRY LEE |
| Corrections Issued | 10/1/2018 | LARRY LEE |
| Quality Review Completed | 10/4/2018 | CHARLES CHANG |
| Building Plans Picked Up | 10/10/2018 | APPLICANT |
| Applicant returned to address corrections | 11/1/2018 | LARRY LEE |
| Plan Check Approved | 1/17/2019 | LARRY LEE |
| Issued | 1/18/2019 | LADBS |
| Permit Finaled | 9/27/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/27/2018 | RYAN HUDSON |
| "D" conditions | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| "Q" conditions | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| CPC | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| CPC | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 12/4/2018 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2018 | NAZILA NOORIFAR |
| Highway dedication | Cleared | 12/6/2018 | NAZILA NOORIFAR |
| Miscellaneous | Cleared | 12/6/2018 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 12/6/2018 | NAZILA NOORIFAR |
| City Hist. Cultural Monument | Cleared | 12/11/2018 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 12/11/2018 | LAMBERT GIESSINGER |
| Green Code | Cleared | 12/13/2018 | KHEDER ALRAZAA |
| Historical monument | Cleared | 12/14/2018 | JIM URQUHART |
| Project located in CRA area | Cleared | 12/14/2018 | JIM URQUHART |
| DAS Clearance | Cleared | 12/20/2018 | WAI LAU |
| Fire Marshall Fire Life Safety | Cleared | 1/15/2019 | OSCAR SALGADO JR |
Contact Information
| Architect | Liljegren, Karin J; Lic. No.: C28158 | 727 W 7TH STREET # 610 LOS ANGELES, CA 90017 |
| Contractor | M D M Builders Group; Lic. No.: 933238-B | 541 SOUTH SPRING ST STE 213 LOS ANGELES, CA 90013 |
| Engineer | Gharibans, Edmond T; Lic. No.: S2942 | 18544 BRYMER STREET NORTHRIDGE, CA 913261951 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 7/29/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 8/6/2019 | Conditional Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 10/1/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Reinforced Concrete Frame | 10/2/2019 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 10/9/2019 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/12/2019 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 12/2/2019 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 1/7/2020 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 1/14/2020 | Conditional Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 1/21/2020 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 2/5/2020 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 2/13/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 2/21/2020 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 3/9/2020 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 4/15/2020 | Partial Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 4/15/2020 | Partial Approval | DANIEL COLLINS |
| Final | 9/23/2021 | Partial Inspection | ERNESTO CORRAL |
| Green Building Final | 9/23/2021 | Approved | ERNESTO CORRAL |
| Final | 9/27/2021 | Permit Finaled | DANIEL COLLINS |