2436 N JUPITER DR 90046
Certificate Information: 2436 N JUPITER DR 90046
- Application / Permit
- 18014-10001-07151
- Plan Check / Job No.
- B20LA04716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT 18014-30000-07151. REVISE LAYOUT, INCREASE ADDITION, AND CHANGE ENGINEER OF RECORD
- Permit Issued
- Issued on 5/11/2020
- Issuing Office
- Current Status
- Permit Finaled on 10/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | LAMAR DAVIS |
| Corrections Issued | 3/23/2020 | LAMAR DAVIS |
| Quality Review Completed | 4/2/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/16/2020 | LAMAR DAVIS |
| Plan Check Approved | 5/6/2020 | LAMAR DAVIS |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Issued | 5/11/2020 | APPLICANT |
| Green Plans Picked Up | 6/12/2020 | APPLICANT |
| Permit Finaled | 10/30/2023 | BRIAN SULLIVAN |
Permit Application Clearance Information
| ZA Case | Cleared | 4/13/2020 | JOE LUCKEY |
| BHO/Hillside ordinance | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 4/15/2020 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 4/16/2020 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 4/16/2020 | ROBERT HUGHES |
| Green Code | Cleared | 4/23/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 4/23/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/24/2020 | DINAH GARIN |
Contact Information
| Contractor | Farahmand Development Company Inc; Lic. No.: 741156-B | 8671 WILSHIRE BLVD #718 BEVERLY HILLS, CA 90211 |
| Engineer | Jafari,, Masoud; Lic. No.: S3812 | 23 ORCHARD SUITE 250 LAKE FOREST, CA 92630 |
| Engineer | Miscione,, Frank Vincent; Lic. No.: C69031 | 30014 LEXINGTON VAL VERDE, CA 91384 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2020 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/18/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 9/30/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Drilled-In Anchors | 10/1/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/2/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/6/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 2/8/2021 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 2/9/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 2/10/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/11/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 9/13/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 9/15/2021 | Approved | RAUL BARAJAS |
| HVAC-Rough | 11/5/2021 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 11/10/2021 | Corrections Issued | RAUL BARAJAS |
| HVAC-Rough | 11/10/2021 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/23/2021 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 12/7/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 12/7/2021 | Partial Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 12/10/2021 | Conditional Approval | RAUL BARAJAS |
| Wood Frame | 12/21/2021 | Conditional Approval | RAUL BARAJAS |
| Sewer | 1/5/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/18/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 2/2/2022 | Approved | RAUL BARAJAS |
| Underground Mechanical | 4/27/2022 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 6/1/2022 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 6/1/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/2/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 8/23/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/2/2022 | Approved | RAUL BARAJAS |
| Underground Mechanical | 5/15/2023 | Partial Approval | STUART CHAPMAN |
| Service/Power Release | 6/27/2023 | Corrections Issued | STUART CHAPMAN |
| Service/Power Release | 7/6/2023 | Partial Inspection | RAUL BARAJAS |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 8/1/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Service/Power Release | 8/1/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 9/26/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 9/26/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 10/13/2023 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 10/23/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/23/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 10/23/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 10/23/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 10/30/2023 | Approved | BRIAN SULLIVAN |
| Final | 10/30/2023 | Permit Finaled | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/30/2023 | Approved | BRIAN SULLIVAN |
| Green Building Final | 10/30/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/30/2023 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/30/2023 | Approved | BRIAN SULLIVAN |