4919 E LINCOLN AVE 90042

Certificate Information: 4919 E LINCOLN AVE 90042

Application / Permit
18014-10000-06995
Plan Check / Job No.
B18LA26396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU 2-STORY ADU PER SB 229 AND AB 494 ATTACHED TO (E) 1-STORY GARAGE
Permit Issued
Issued on 5/23/2019
Issuing Office
Metro
Current Status
Issued on 5/23/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/7/2018 APPLICANT
Assigned to Plan Check Engineer 12/27/2018 ANA AVELAR
Corrections Issued 1/2/2019 ANA AVELAR
Quality Review Completed 1/9/2019 KESETE HAREGOT
Building Plans Picked Up 2/15/2019 APPLICANT
Green Plans Picked Up 2/25/2019 APPLICANT
Applicant returned to address corrections 4/10/2019 ANA AVELAR
Applicant returned to address corrections 5/3/2019 ANA AVELAR
Plan Check Approved 5/21/2019 JOSE RODRIGUEZ
Issued 5/23/2019 LADBS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/15/2019 PATRICK MISCHLICH
Hydrant and Access approval Cleared 3/15/2019 GEORGE SUCHAND
Green Code Cleared 3/21/2019 COLIN LOREDO
GPI Written Notices Cleared 5/3/2019 ANA AVELAR
Address approval Cleared 5/7/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/7/2019 ELAINE LEI
Low Impact Development Cleared 5/7/2019 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 5/7/2019 ELAINE LEI
Sewer availability Cleared 5/7/2019 ELAINE LEI

Contact Information

Contractor Pro Builders Express Inc; Lic. No.: 737610-B 14408 WHITTIER BLVD B9      WHITTIER, CA 90605
Engineer Byon,, Jin Sop; Lic. No.: C45122 2504 SIERRA LEONE AVE      ROWLAND HEIGHTS, CA 91748

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/20/2019 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 6/25/2019 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 7/3/2019 Conditional Approval RUBEN SALAS
BUILDING-Rough-Frame 9/30/2019 Corrections Issued CRAIG VAUGHAN
Green Building Rough 9/30/2019 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 10/11/2019 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 10/11/2019 Conditional Approval CRAIG VAUGHAN
Green Building Rough 10/11/2019 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2019 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/22/2019 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 10/22/2019 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 10/22/2019 Not Ready for Inspection BRIAN SULLIVAN
Pool Piping 10/22/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/30/2019 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 10/30/2019 Corrections Issued RUBEN SALAS
Green Building Rough 10/30/2019 Approved RUBEN SALAS
PLUMBING-Rough 10/30/2019 Corrections Issued RUBEN SALAS
Rough-Elec/Plmb/HVAC 11/4/2019 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/7/2019 No Access for Inspection CRAIG VAUGHAN
HVAC-Rough 11/7/2019 No Access for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/7/2019 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 12/11/2019 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 12/11/2019 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 12/11/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/13/2020 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 2/19/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 2/19/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 2/19/2020 Approved CRAIG VAUGHAN
Wood Frame 2/19/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 2/25/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/2/2020 Partial Approval CRAIG VAUGHAN
Insulation 7/10/2020 Approved CRAIG VAUGHAN
Drywall Nailing 7/15/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/23/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/25/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 11/25/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 11/25/2020 Approved CRAIG VAUGHAN
Green Building Final 11/25/2020 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 11/25/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 3/30/2021 Partial Approval CRAIG VAUGHAN
Final 3/30/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 3/30/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 3/30/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/9/2021 Approved CRAIG VAUGHAN
Final 4/9/2021 Conditional Approval CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved CRAIG VAUGHAN