4312 E YORK BLVD 90041
Certificate Information: 4312 E YORK BLVD 90041
- Application / Permit
- 18014-10000-06918
- Plan Check / Job No.
- B18LA26140
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 55 SF ADDITION BETWEEN EXISTING DETACHED GARAGE AND EXISTING TOOL SHED, THEN CONVERTING ALL TO A SINGLE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB229 (370sqft)
- Permit Issued
- Issued on 6/7/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2018 | APPLICANT |
| Green Plans Picked Up | 12/13/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | LUIS RINCON |
| Corrections Issued | 1/2/2019 | LUIS RINCON |
| Quality Review Completed | 1/3/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 1/24/2019 | APPLICANT |
| Plan Check Approved | 4/24/2019 | LUIS RINCON |
| Issued | 6/7/2019 | LADBS |
| CofO in Progress | 4/3/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/13/2020 | DEROLD HAUFF |
| CofO Issued | 10/13/2020 | DEROLD HAUFF |
| Permit Finaled | 10/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2019 | KAREN LE |
| Grading Pre-Inspection | Cleared | 1/24/2019 | BARTON HOLMES |
| Roof/Waste drainage to street | Cleared | 1/24/2019 | KAREN LE |
| Sewer availability | Cleared | 1/29/2019 | JEANIE LAM |
| Green Code | Cleared | 2/4/2019 | KHEDER ALRAZAA |
| Supp. Use District POD/CDO/TDO | Cleared | 3/28/2019 | NICOLE SANCHEZ |
| ZI | Cleared | 3/28/2019 | NICOLE SANCHEZ |
| Address approval | Cleared | 4/22/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2019 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/15/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 11/18/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/27/2019 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/13/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/13/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 12/13/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/17/2019 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/17/2019 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/23/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 12/23/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 12/23/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 12/23/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/30/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/15/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 1/15/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/15/2020 | Approved | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 1/16/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 1/17/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/22/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/22/2020 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/22/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/24/2020 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 1/28/2020 | Approved | CHARLES BOGHOSKHAN |
| Green Building Rough | 1/28/2020 | Approved | CHARLES BOGHOSKHAN |
| Final | 2/14/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/14/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/14/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 2/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 2/26/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 3/4/2020 | Conditional Approval | CHARLES BOGHOSKHAN |
| Green Building Final | 3/4/2020 | Approved | CHARLES BOGHOSKHAN |
| Final | 4/3/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |