4312 E YORK BLVD 90041

Certificate Information: 4312 E YORK BLVD 90041

Application / Permit
18014-10000-06918
Plan Check / Job No.
B18LA26140
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
55 SF ADDITION BETWEEN EXISTING DETACHED GARAGE AND EXISTING TOOL SHED, THEN CONVERTING ALL TO A SINGLE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB229 (370sqft)
Permit Issued
Issued on 6/7/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/13/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2018 APPLICANT
Green Plans Picked Up 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 LUIS RINCON
Corrections Issued 1/2/2019 LUIS RINCON
Quality Review Completed 1/3/2019 MOHAMMAD FIROUZBAKHT
Building Plans Picked Up 1/24/2019 APPLICANT
Plan Check Approved 4/24/2019 LUIS RINCON
Issued 6/7/2019 LADBS
CofO in Progress 4/3/2020 HAMIK HARTOUNIAN
Permit Finaled 10/13/2020 DEROLD HAUFF
CofO Issued 10/13/2020 DEROLD HAUFF
Permit Finaled 10/13/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2019 KAREN LE
Grading Pre-Inspection Cleared 1/24/2019 BARTON HOLMES
Roof/Waste drainage to street Cleared 1/24/2019 KAREN LE
Sewer availability Cleared 1/29/2019 JEANIE LAM
Green Code Cleared 2/4/2019 KHEDER ALRAZAA
Supp. Use District POD/CDO/TDO Cleared 3/28/2019 NICOLE SANCHEZ
ZI Cleared 3/28/2019 NICOLE SANCHEZ
Address approval Cleared 4/22/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2019 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 11/15/2019 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 11/18/2019 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/27/2019 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/13/2019 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 12/13/2019 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 12/13/2019 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/17/2019 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 12/17/2019 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/23/2019 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 12/23/2019 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 12/23/2019 Not Ready for Inspection BRIAN SULLIVAN
Sewer 12/23/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/30/2019 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/15/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 1/15/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/15/2020 Approved HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/16/2020 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 1/17/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/22/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 1/22/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 1/22/2020 Approved HAMIK HARTOUNIAN
Insulation 1/24/2020 Approved CHARLES BOGHOSKHAN
Drywall Nailing 1/28/2020 Approved CHARLES BOGHOSKHAN
Green Building Rough 1/28/2020 Approved CHARLES BOGHOSKHAN
Final 2/14/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/14/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/14/2020 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/14/2020 Approved HAMIK HARTOUNIAN
Sewer 2/20/2020 Conditional Approval HAMIK HARTOUNIAN
Final 2/26/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/26/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 3/4/2020 Conditional Approval CHARLES BOGHOSKHAN
Green Building Final 3/4/2020 Approved CHARLES BOGHOSKHAN
Final 4/3/2020 OK to Issue CofO HAMIK HARTOUNIAN