3715 N LOWELL AVE 90032
Certificate Information: 3715 N LOWELL AVE 90032
- Application / Permit
- 18014-10000-06748
- Plan Check / Job No.
- B18LA25344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage to accessory dwelling unit per AB494 and SB229 and new 20'x 41'-6" ground floor addition to accessory dwelling unit
- Permit Issued
- Issued on 8/13/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/31/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2018 | VU NGUYEN |
| Corrections Issued | 1/2/2019 | VU NGUYEN |
| Quality Review Completed | 1/3/2019 | MICHAEL PEREZ |
| Green Plans Picked Up | 1/4/2019 | APPLICANT |
| Building Plans Picked Up | 1/8/2019 | APPLICANT |
| Applicant returned to address corrections | 6/26/2019 | VU NGUYEN |
| Plan Check Approved | 6/27/2019 | VU NGUYEN |
| Issued | 8/13/2019 | LADBS |
| CofO in Progress | 7/28/2020 | ENRIQUE MIRELES |
| CofO in Progress | 7/28/2020 | ENRIQUE MIRELES |
| Permit Finaled | 8/31/2020 | DEROLD HAUFF |
| Permit Finaled | 8/31/2020 | DEROLD HAUFF |
| CofO Issued | 8/31/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 5/30/2019 | KHEDER ALRAZAA |
| Address approval | Cleared | 6/4/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2019 | ROBYN STEELE |
| Sewer availability | Cleared | 6/19/2019 | ROBYN STEELE |
| Construction near power lines | Cleared | 6/24/2019 | NADER ISKANDER |
| Low Impact Development | Cleared | 6/24/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/24/2019 | CELINA MORENO |
| GPI Written Notices | Cleared | 6/26/2019 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 6/26/2019 | VU NGUYEN |
Contact Information
| Contractor | Seven Star Int'L Development & Construction Inc; Lic. No.: 998628-B | 1452 LAWFORD ST GLENDORA, CA 91741 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/19/2019 | Approved | ENRIQUE MIRELES |
| Sewer | 9/11/2019 | Corrections Issued | RUBEN SALAS |
| Underground Mechanical | 9/11/2019 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 9/19/2019 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/27/2019 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2019 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 10/30/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/18/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/18/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 11/18/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/18/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/21/2019 | Corrections Issued | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2019 | Not Ready for Inspection | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 11/27/2019 | Approved | ENRIQUE MIRELES |
| Insulation | 12/3/2019 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/3/2019 | Partial Approval | ENRIQUE MIRELES |
| Drywall Nailing | 12/12/2019 | Conditional Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 12/12/2019 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Final | 1/10/2020 | Corrections Issued | BRAD BESCOS |
| BUILDING-Rough-Frame | 2/27/2020 | Corrections Issued | ENRIQUE MIRELES |
| Final | 2/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 2/27/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/27/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 2/27/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 3/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/9/2020 | SGSOV Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/17/2020 | Approved | ENRIQUE MIRELES |
| Final | 3/17/2020 | Corrections Issued | ENRIQUE MIRELES |
| Final | 7/1/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 7/6/2020 | Conditional Approval | ENRIQUE MIRELES |
| Service/Power Release | 7/6/2020 | Approved | ENRIQUE MIRELES |
| Final | 7/28/2020 | OK to Issue CofO | ENRIQUE MIRELES |