5234-5234 1/2 E LINCOLN AVE 90042

Certificate Information: 5234-5234 1/2 E LINCOLN AVE 90042

Application / Permit
18014-10000-06683
Plan Check / Job No.
B18LA25124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITON TO (E) SFD AT REAR. THE ADDITION EXTENDS TO EXISTING DETACHED GARAGE/REC ROOM RESULTING A ONE SINGLE FAMILY DWELLING (SFD) WITH ATTACHED ACCESSORY DWELLING UNIT (ADU) & 1-CAR GARAGE.
Permit Issued
Issued on 5/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 MONICA RAMIREZ
Corrections Issued 12/24/2018 MONICA RAMIREZ
Green Plans Picked Up 1/10/2019 APPLICANT
Quality Review Completed 1/11/2019 HERNAN ARREOLA
Building Plans Picked Up 1/17/2019 APPLICANT
Plan Check Approved 4/29/2019 MONICA RAMIREZ
No Progress 4/30/2019 MONICA RAMIREZ
Plan Check Approved 5/1/2019 MONICA RAMIREZ
Issued 5/2/2019 LADBS
CofO in Progress 9/22/2020 CRAIG VAUGHAN
Permit Finaled 10/2/2020 DEROLD HAUFF
CofO Issued 10/2/2020 DEROLD HAUFF
Permit Finaled 10/2/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/27/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/27/2019 CELINA MORENO
Hydrant and Access approval Cleared 3/27/2019 GILBERT URREA
Sewer availability Cleared 3/27/2019 CELINA MORENO
Low Impact Development Cleared 4/8/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/8/2019 ERIK BEASLEY
Green Code Cleared 4/9/2019 KHEDER ALRAZAA
Grading Pre-Inspection Cleared 4/12/2019 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/28/2019 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/30/2019 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 5/30/2019 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/18/2019 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/21/2019 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/21/2019 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/25/2019 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/8/2019 Corrections Issued CRAIG VAUGHAN
Green Building Rough 7/8/2019 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/8/2019 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/15/2019 Partial Approval CRAIG VAUGHAN
Sewer 7/15/2019 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2019 Partial Approval KATHRYN BUTTERWORTH
Sewer 8/12/2019 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 10/3/2019 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 10/3/2019 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 10/3/2019 Corrections Issued BRIAN SULLIVAN
Sewer 10/3/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/8/2019 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/8/2019 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/8/2019 Approved CRAIG VAUGHAN
HVAC-Rough 10/8/2019 Approved CRAIG VAUGHAN
PLUMBING-Rough 10/8/2019 Conditional Approval CRAIG VAUGHAN
Sewer 10/8/2019 Not Ready for Inspection CRAIG VAUGHAN
Sewer 10/25/2019 Approved RUBEN SALAS
Interior/Exterior Lathing 10/30/2019 Partial Approval RUBEN SALAS
Interior/Exterior Lathing 11/12/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 12/2/2019 Corrections Issued LUIS BARRALES
Insulation 12/5/2019 Approved MICHAEL FAUNCE
Drywall Nailing 12/16/2019 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 1/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 1/14/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/13/2020 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 4/29/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/29/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 4/29/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 4/29/2020 Corrections Issued CRAIG VAUGHAN
Green Building Rough 4/29/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 4/29/2020 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/29/2020 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 4/29/2020 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 5/5/2020 Approved CRAIG VAUGHAN
Final 5/5/2020 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 5/5/2020 Approved CRAIG VAUGHAN
Green Building Final 5/5/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 5/5/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/5/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/5/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 5/12/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 5/12/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 5/12/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/28/2020 Approved CRAIG VAUGHAN
Final 7/28/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/28/2020 Approved CRAIG VAUGHAN
Final 8/4/2020 Conditional Approval CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Approved CRAIG VAUGHAN
Final 9/21/2020 Conditional Approval CRAIG VAUGHAN