1908 N LEMOYNE ST 90026
Certificate Information: 1908 N LEMOYNE ST 90026
- Application / Permit
- 18014-10000-06659
- Plan Check / Job No.
- B18LA25007
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF NEW LOWER LEVEL HABITABLE SPACE, 1ST LEVEL , AND NEW ATTACHED GARAGE; INTERIOR REMODEL TO (E) 1 STORY SFD. BUILDING SHALL BE EQUIPPED WITH AUTOMATIC FIRE SPRINKLER SYSTEM. PERMIT 1 OF 2
- Permit Issued
- Issued on 10/1/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2018 | JEFFREY MACHADO |
| Corrections Issued | 12/10/2018 | JEFFREY MACHADO |
| Quality Review Completed | 12/12/2018 | FELIX FIGUEROA |
| Building Plans Picked Up | 12/13/2018 | APPLICANT |
| Green Plans Picked Up | 12/13/2018 | APPLICANT |
| Plan Check Approved | 8/22/2019 | JEFFREY MACHADO |
| Issued | 10/1/2019 | LADBS |
| CofO in Progress | 7/28/2022 | RUBEN SALAS |
| Permit Finaled | 7/28/2022 | DEROLD HAUFF |
| CofO Issued | 7/28/2022 | DEROLD HAUFF |
| Permit Finaled | 7/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/25/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 4/25/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 4/25/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 4/25/2019 | ELENA LOPEZ |
| Green Code | Cleared | 5/2/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 5/16/2019 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 5/31/2019 | NGOC KIEM |
| GPI Written Notices | Cleared | 8/22/2019 | JEFFREY MACHADO |
| Grading Pre-Inspection | Cleared | 8/22/2019 | JEFFREY MACHADO |
Contact Information
| Architect | Elbogen,, Robert Andrew; Lic. No.: C22948 | 16240 DICKENS ST ENCINO, CA 91436 |
| Contractor | Analog Construction; Lic. No.: 1058496-B | 1910 W SUNSET BLVD #660 LOS ANGELES, CA 90026 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 4/9/2021 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/28/2021 | Partial Approval | ROBERT VORHIS |
| Green Building Final | 6/28/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 6/28/2021 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 6/28/2021 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/9/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 7/9/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 7/9/2021 | Partial Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 7/9/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/23/2021 | Approved | THOMAS LOGRASSO |
| Shower Pan | 7/23/2021 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 4/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/27/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 4/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 4/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 4/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| Reinforced Concrete Frame | 4/27/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 4/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 4/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 5/31/2022 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 5/31/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 5/31/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 5/31/2022 | Approved | THOMAS LOGRASSO |
| Final | 6/20/2022 | Not Ready for Inspection | RUBEN SALAS |
| Gas Test | 6/20/2022 | Approved | RUBEN SALAS |
| Green Building Final | 6/20/2022 | Approved | RUBEN SALAS |
| Service/Power Release | 6/20/2022 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 6/23/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 6/23/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 6/23/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 6/23/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 6/30/2022 | Approved | THOMAS LOGRASSO |
| Final | 6/30/2022 | Corrections Issued | THOMAS LOGRASSO |
| Grounding or Bonding | 6/30/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 6/30/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 6/30/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 6/30/2022 | Approved | THOMAS LOGRASSO |
| Final | 7/28/2022 | OK to Issue CofO | RUBEN SALAS |