12136 W CLARKSON ROAD 90064

Certificate Information: 12136 W CLARKSON ROAD 90064

Application / Permit
18014-10000-06627
Plan Check / Job No.
B18LA24901
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 47'-6" X 65' TO EXISTING SINGLE FAMILY DWELLING TO ADD NEW BEDROOM AND ENALRGE LIVING ROOM AND CONVERT 10'5" X 20'-2" 1 CAR GARAGE TO NEW 1/2 BATHROOM WITH LAUNDRY ROOM.
Permit Issued
Issued on 4/16/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2018 APPLICANT
Green Plans Picked Up 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 12/20/2018 MICHAEL PEREZ
Corrections Issued 1/2/2019 MICHAEL PEREZ
Quality Review Completed 1/17/2019 QUAN NGHIEM
Building Plans Picked Up 1/22/2019 APPLICANT
Plan Check Approved 4/4/2019 MICHAEL PEREZ
Issued 4/16/2019 LADBS
CofO in Progress 6/23/2022 JOHNNY MIRANDA
Permit Finaled 8/2/2022 DANIEL ORRANTE
CofO Issued 8/2/2022 DANIEL ORRANTE
Permit Finaled 8/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 1/22/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 1/22/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 1/22/2019 SOPHIE GABEL-SCHEINBAU
Green Code Cleared 2/4/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/1/2019 ZIXUAN CHEN
Low Impact Development Cleared 4/1/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/1/2019 ZIXUAN CHEN
Sewer availability Cleared 4/1/2019 ZIXUAN CHEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/13/2019 Conditional Approval KEVIN BEAULIEU
Excavation/Setback/Form/Re-Bar 5/22/2019 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 5/29/2019 Conditional Approval KEVIN BEAULIEU
Footing/Foundation/Slab 6/6/2019 Not Ready for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 6/24/2019 Partial Approval KEVIN BEAULIEU
Green Building Rough 6/24/2019 Not Ready for Inspection KEVIN BEAULIEU
Pre-Inspection 8/8/2019 No Access for Inspection KEVIN BEAULIEU
BUILDING-Rough-Frame 8/27/2019 Conditional Approval KEVIN BEAULIEU
Green Building Rough 8/27/2019 Conditional Approval KEVIN BEAULIEU
BUILDING-Rough-Frame 9/20/2019 Not Ready for Inspection KEVIN BEAULIEU
Green Building Rough 9/20/2019 Not Ready for Inspection KEVIN BEAULIEU
HVAC-Rough 9/20/2019 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 9/20/2019 Not Ready for Inspection KEVIN BEAULIEU
ELECTRICAL-Rough 9/25/2019 Not Ready for Inspection KEVIN BEAULIEU
HVAC-Rough 9/25/2019 Approved KEVIN BEAULIEU
ELECTRICAL-Rough 10/1/2019 Approved KEVIN BEAULIEU
BUILDING-Rough-Frame 11/8/2019 Approved KEVIN BEAULIEU
Green Building Rough 11/8/2019 Approved KEVIN BEAULIEU
Insulation 11/19/2019 Approved KEVIN BEAULIEU
Shower Pan 11/19/2019 Approved KEVIN BEAULIEU
Drywall Nailing 11/26/2019 Approved KEVIN BEAULIEU
Interior/Exterior Lathing 12/3/2019 Approved KEVIN BEAULIEU
Service/Power Release 5/26/2020 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Final 7/17/2020 Approved JUSTIN CURTIS
ELECTRICAL-Final 11/19/2020 Approved RICHARD ROBLES
Service/Power Release 11/19/2020 Corrections Issued RICHARD ROBLES
ELECTRICAL-Final 12/16/2020 No Access for Inspection JOHNNY MIRANDA
Service/Power Release 12/16/2020 No Access for Inspection JOHNNY MIRANDA
Service/Power Release 12/24/2020 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Not Ready EVAN COOPER
HVAC-Final 7/20/2021 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Final 7/20/2021 Approved KENNETH NAGLE
Final 8/11/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 8/11/2021 Not Ready for Inspection EVAN COOPER
Green Building Final 8/11/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Not Ready EVAN COOPER
Smoke Detectors 8/11/2021 Approved EVAN COOPER
Final 6/16/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/16/2022 Approved JOHNNY MIRANDA
Green Building Final 6/16/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready JOHNNY MIRANDA
Final 6/22/2022 OK to Issue CofO JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JOHNNY MIRANDA