7202 W LONZO ST 91042

Certificate Information: 7202 W LONZO ST 91042

Application / Permit
18014-10000-06591
Plan Check / Job No.
B18LA24761
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New addition to existing Single Family Dwelling with Roof Deck, and add attached Patio over. Also, include Kitchen remodel.
Permit Issued
Issued on 2/22/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 11/30/2018 SERGIO GUTIERREZ
Corrections Issued 12/11/2018 SERGIO GUTIERREZ
Green Plans Picked Up 12/19/2018 APPLICANT
Quality Review Completed 12/26/2018 TIEN JEN WANG
Building Plans Picked Up 1/28/2019 APPLICANT
Applicant returned to address corrections 2/1/2019 SERGIO GUTIERREZ
Plan Check Approved 2/22/2019 SERGIO GUTIERREZ
Issued 2/22/2019 LADBS
CofO in Progress 12/4/2020 MATTHEW NELSON
Permit Finaled 12/26/2020 MICHAEL SMITH
CofO Issued 12/26/2020 MICHAEL SMITH
Permit Finaled 12/26/2020 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/28/2019 KAREN LE
BHO/Hillside ordinance Cleared 1/28/2019 KAREN LE
BHO/Hillside ordinance Cleared 1/28/2019 KAREN LE
Eng Process Fee Ord 176,300 Cleared 1/28/2019 KAREN LE
Sewer availability Cleared 1/28/2019 KAREN LE
Tract Map conditions Cleared 1/28/2019 NORA DRESSER
Construction near power lines Cleared 1/30/2019 OSCAR CASTRO
Grading Pre-Inspection Cleared 1/30/2019 PATRICK MISCHLICH
Low Impact Development Cleared 2/20/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/20/2019 ERIK BEASLEY
Green Code Cleared 2/21/2019 COLIN LOREDO

Contact Information

Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/5/2019 Corrections Issued JOHN HAYES
PLUMBING-Rough 3/5/2019 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 3/8/2019 Approved JOHN HAYES
PLUMBING-Rough 3/8/2019 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Approved MATTHEW NELSON
Shower Pan 5/13/2019 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/20/2019 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 5/20/2019 Corrections Issued MATTHEW NELSON
HVAC-Rough 5/20/2019 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 5/20/2019 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/11/2019 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 6/11/2019 Approved MATTHEW NELSON
Green Building Rough 6/11/2019 Approved MATTHEW NELSON
HVAC-Rough 6/11/2019 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/11/2019 Approved MATTHEW NELSON
Insulation 6/19/2019 Approved MATTHEW NELSON
Drywall Nailing 6/27/2019 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/22/2019 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/28/2019 Approved MATTHEW NELSON
Final 10/28/2019 Corrections Issued MATTHEW NELSON
Green Building Final 10/28/2019 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/28/2019 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/28/2019 Approved MATTHEW NELSON
ELECTRICAL-Final 11/1/2019 Approved MATTHEW NELSON
HVAC-Final 11/1/2019 Approved MATTHEW NELSON
Final 10/28/2020 Partial Inspection MATTHEW NELSON
Green Building Final 10/28/2020 Approved MATTHEW NELSON
PLUMBING-Final 10/28/2020 Approved MATTHEW NELSON
Final 11/18/2020 Corrections Issued MATTHEW NELSON
Final 12/4/2020 OK to Issue CofO MATTHEW NELSON