3787 1/2 S CIMARRON ST 90018
Certificate Information: 3787 1/2 S CIMARRON ST 90018
- Application / Permit
- 18014-10000-06556
- Plan Check / Job No.
- B18LA24616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Single-story addition to (E) single-story garage and conversion to ADU.
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 1/8/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/15/2018 | APPLICANT |
| Green Plans Picked Up | 11/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | RODOLFO ARIAS |
| Corrections Issued | 12/3/2018 | RODOLFO ARIAS |
| Quality Review Completed | 12/7/2018 | GARO TELMI |
| Building Plans Picked Up | 12/11/2018 | APPLICANT |
| Applicant returned to address corrections | 4/30/2019 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/11/2019 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/25/2019 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/7/2019 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/29/2019 | RODOLFO ARIAS |
| Applicant returned to address corrections | 9/17/2019 | RODOLFO ARIAS |
| Plan Check Approved | 9/27/2019 | RODOLFO ARIAS |
| Issued | 1/8/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2019 | JEANETTE VONG |
| Permit | Cleared | 1/30/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2019 | CELINA MORENO |
| Sewer availability | Cleared | 2/6/2019 | CELINA MORENO |
| Green Code | Cleared | 2/25/2019 | RODOLFO ARIAS |
| Construction near power lines | Cleared | 3/22/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/16/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/16/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/16/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/16/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/16/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 3/16/2020 | Corrections Issued | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/16/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 3/23/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 3/23/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 4/6/2020 | Approved | SABAS ALONSO |
| Gas Test | 2/5/2021 | No Access for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 2/5/2021 | No Access for Inspection | ROBERT MCDOWELL |
| Gas Test | 2/10/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/10/2021 | Approved | ROBERT MCDOWELL |
| Final | 11/1/2021 | No Access for Inspection | SABAS ALONSO |
| Green Building Final | 11/1/2021 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/1/2021 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 12/2/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/2/2021 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/2/2021 | Approved | SABAS ALONSO |
| HVAC-Final | 12/2/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/2/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 12/2/2021 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 12/2/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/29/2022 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 4/29/2022 | Approved | SABAS ALONSO |
| Service/Power Release | 4/29/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/30/2022 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | SABAS ALONSO |
| ELECTRICAL-Final | 7/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 7/27/2022 | No Access for Inspection | SABAS ALONSO |