2927 1/2 E ALTURA ST 90031

Certificate Information: 2927 1/2 E ALTURA ST 90031

Application / Permit
18014-10000-06437
Plan Check / Job No.
B18LA24217
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDITION TO EXISTING GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. P.C. SEE COMMENTS
Permit Issued
Issued on 8/9/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2018 APPLICANT
Assigned to Plan Check Engineer 11/16/2018 MICHAEL LOPEZ
Corrections Issued 11/16/2018 MICHAEL LOPEZ
Applicant returned to address corrections 8/6/2019 EMMANUEL MARTINEZ
Plan Check Approved 8/9/2019 ADAM HEGAZI
Issued 8/9/2019 LADBS
CofO in Progress 11/2/2020 OSVALDO PARAMO
CofO in Progress 11/2/2020 OSVALDO PARAMO
CofO in Progress 11/2/2020 OSVALDO PARAMO
Permit Finaled 11/20/2020 DEROLD HAUFF
CofO Issued 11/20/2020 DEROLD HAUFF
Permit Finaled 11/20/2020 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 12/31/2018 JONATHAN KAPLAN
CPC Cleared 12/31/2018 JONATHAN KAPLAN
Address approval Cleared 5/10/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/10/2019 ELENA LOPEZ
Grading Pre-Inspection Cleared 5/10/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 5/10/2019 ELENA LOPEZ
Sewer availability Cleared 5/10/2019 ELENA LOPEZ
HPOZ Cleared 5/30/2019 JONATHAN KAPLAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/13/2019 Approved OSVALDO PARAMO
Underground Mechanical 10/15/2019 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 10/17/2019 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/22/2019 Approved OSVALDO PARAMO
Footing/Foundation/Slab 10/22/2019 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 4/2/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/3/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 6/3/2020 Approved OSVALDO PARAMO
HVAC-Rough 6/8/2020 Approved OSVALDO PARAMO
Wood Frame 6/8/2020 Approved OSVALDO PARAMO
Underground Mechanical 6/11/2020 Partial Approval OSVALDO PARAMO
Wood Frame 6/11/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 6/17/2020 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 7/31/2020 Not Ready for Inspection ELMER BLAND
Insulation 8/5/2020 Approved CHRISTOPHER DELLEFIELD
Shower Pan 8/5/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 8/19/2020 Approved DAVID MATSON
Shower Pan 8/19/2020 Approved DAVID MATSON
Interior/Exterior Lathing 8/26/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/23/2020 Approved OSVALDO PARAMO
Final 10/23/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 10/23/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 10/23/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/23/2020 Approved OSVALDO PARAMO
Final 10/30/2020 OK to Issue CofO OSVALDO PARAMO
Green Building Final 10/30/2020 Approved OSVALDO PARAMO