1121 S GLENDON AVE 90024

Certificate Information: 1121 S GLENDON AVE 90024

Application / Permit
18014-10000-06350
Plan Check / Job No.
B18LA23824
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
DEMO AND REBUILD NEW RESTROOM AND CORRIODR AT FIRST FLOOR. TENANT IMPROVEMENT TO EXISTING RESTAURANT. TENANT IMPROVEMENT AT 2ND FLOOR FOR DINING SPACE AND SECOND KITCHEN ACCESSORY TO MAIN RESTAURANT. NEW UNCOVERED OUTDOOR EATING AREA @ COURT YARD. (NEW RETRACTABLE AWNING & NEW GLASS ROOF @ COURTYARD ON SEPARATE PERMIT)
Permit Issued
Issued on 1/23/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 JOE VO
Green Plans Picked Up 11/20/2018 APPLICANT
Corrections Issued 11/26/2018 JOE VO
Quality Review Completed 11/29/2018 GARO TELMI
Building Plans Picked Up 12/3/2018 APPLICANT
Disabled Access Plans Picked Up 12/4/2018 APPLICANT
Applicant returned to address corrections 12/13/2018 JOE VO
Applicant returned to address corrections 1/4/2019 JOE VO
Plan Check Approved 1/22/2019 JOE VO
Issued 1/23/2019 LADBS
TCO Issued (Expire Date: 08-23-2020) 2/25/2020 TED RIES
CofO in Progress 3/31/2020 PAUL DAVIDSON
Permit Finaled 4/1/2020 TED RIES
CofO Issued 4/1/2020 TED RIES
Permit Finaled 4/1/2020 TED RIES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/11/2018 MICHAEL CASTILLO
Low Impact Development Cleared 12/13/2018 JORGE MEJIA LEMUS
Historic monument Cleared 12/14/2018 LAMBERT GIESSINGER
Roof/Waste drainage to street Cleared 12/19/2018 ADRIAN SANCHEZ
Sewer availability Cleared 12/19/2018 ADRIAN SANCHEZ
"D" conditions Cleared 12/27/2018 MOTOUMI SASAKI
Comm Cor/Mini-Mall Cleared 12/27/2018 MOTOUMI SASAKI
Comm Cor/Mini-Mall Cleared 12/27/2018 MOTOUMI SASAKI
Specific Plan Cleared 12/27/2018 MOTOUMI SASAKI
ZI Cleared 12/27/2018 MOTOUMI SASAKI
Green Code Cleared 1/2/2019 JOE VO
DAS Clearance Cleared 1/3/2019 EDDIE GARIN
Fire Marshall Fire Life Safety Cleared 1/10/2019 MENOA AGHAJANI
ZA Case Cleared 1/10/2019 DIANA JIMENEZ
Food Service Establishment Cleared 1/17/2019 RAMESHBHAIR PATEL
Food establishment approval Cleared 1/22/2019 LACDHS APPROVED

Contact Information

Architect Schoeplein,, Mark Nicholas; Lic. No.: C24842 960 BLUEGRASS WAY      LOS ANGELES, CA 90049
Engineer Garza,, Omar Leonel; Lic. No.: S5593 4215 TOLAND WAY      LOS ANGELES, CA 90065

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2019 Approved DERRICK SPENCER
Pre-Inspection 3/28/2019 Not Ready for Inspection SORIN CIRSTOIU
Pre-Inspection 3/29/2019 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 4/5/2019 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 4/10/2019 Approved SORIN CIRSTOIU
Masonry Wall/Backfill 4/22/2019 Corrections Issued SORIN CIRSTOIU
Deputy Reinf. Masonry 6/5/2019 Conditional Approval SORIN CIRSTOIU
Green Building Rough 6/6/2019 Partial Inspection SORIN CIRSTOIU
Wall Anchors 6/6/2019 Conditional Approval SORIN CIRSTOIU
Wood Frame 6/6/2019 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 8/30/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 8/30/2019 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 8/30/2019 Partial Inspection SORIN CIRSTOIU
Wood Frame 8/30/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 9/5/2019 Partial Inspection SORIN CIRSTOIU
Wood Frame 9/5/2019 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 9/9/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 10/2/2019 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 10/15/2019 Approved SORIN CIRSTOIU
Structural Steel Frame 10/15/2019 Partial Inspection SORIN CIRSTOIU
T-Bar Ceiling 10/29/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 11/6/2019 Partial Approval SORIN CIRSTOIU
Final 1/29/2020 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 1/29/2020 Partial Inspection SORIN CIRSTOIU
Green Building Final 1/29/2020 Partial Inspection SORIN CIRSTOIU
Green Building Rough 1/29/2020 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 1/29/2020 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 1/29/2020 Not Ready for Inspection SORIN CIRSTOIU
Wood Frame 1/29/2020 Partial Inspection SORIN CIRSTOIU
Final 2/19/2020 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 2/19/2020 Approved PAUL DAVIDSON
Green Building Final 2/19/2020 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 2/19/2020 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 2/19/2020 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 2/19/2020 Approved PAUL DAVIDSON
Wood Frame 2/19/2020 Approved PAUL DAVIDSON
Final 3/31/2020 OK to Issue CofO PAUL DAVIDSON
Green Building Final 3/31/2020 Approved PAUL DAVIDSON