7619 S TRUXTON AVE 90045
Certificate Information: 7619 S TRUXTON AVE 90045
- Application / Permit
- 18014-10000-06244
- Plan Check / Job No.
- B18LA23347
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SFD TO THE FRONT. ENCLOSE ATTACHED PATIO COVER, EXTEND GARAGE, NEW ROOF DECK AT REAR AND MAJOR REMODEL.
- Permit Issued
- Issued on 3/27/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2018 | ADAM HEGAZI |
| Corrections Issued | 12/4/2018 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 12/6/2018 | FELIX FIGUEROA |
| Building Plans Picked Up | 12/11/2018 | APPLICANT |
| Green Plans Picked Up | 12/31/2018 | APPLICANT |
| Plan Check Approved | 3/26/2019 | MONICA RAMIREZ |
| Issued | 3/27/2019 | LADBS |
| CofO in Progress | 1/31/2020 | DAVID FEILER |
| Permit Finaled | 2/11/2020 | VINCENT COTTON |
| CofO Issued | 2/11/2020 | VINCENT COTTON |
| Permit Finaled | 2/11/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/26/2018 | PATRICK MISCHLICH |
| Green Code | Cleared | 1/15/2019 | SARAH ABOULHOSN |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2019 | CELINA MORENO |
| Sewer availability | Cleared | 1/17/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 1/30/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/30/2019 | JEANETTE VONG |
| GPI Written Notices | Cleared | 2/26/2019 | MOHAMMAD FIROUZBAKHT |
Contact Information
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2019 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/17/2019 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/17/2019 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2019 | Partial Approval | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2019 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/5/2019 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/11/2019 | Approved | JUAN VALENZUELA |
| Wood Frame | 8/7/2019 | Corrections Issued | RONALD WEBER |
| BUILDING-Rough-Frame | 8/12/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/12/2019 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 8/12/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 8/12/2019 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/12/2019 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/19/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/19/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/19/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 8/19/2019 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/20/2019 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 8/20/2019 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 9/3/2019 | Conditional Approval | RONALD WEBER |
| Interior/Exterior Lathing | 9/3/2019 | Approved | RONALD WEBER |
| Drywall Nailing | 9/10/2019 | Approved | JUAN VALENZUELA |
| Shower Pan | 9/10/2019 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/13/2019 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/8/2020 | Approved | JUAN VALENZUELA |
| Final | 1/8/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 1/8/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 1/8/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/8/2020 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 1/8/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/10/2020 | Approved | JUAN VALENZUELA |
| Service/Power Release | 1/10/2020 | Approved | JUAN VALENZUELA |
| Final | 1/27/2020 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 1/27/2020 | Approved | DAVID FEILER |