1919 W RIPPLE ST 90039
Certificate Information: 1919 W RIPPLE ST 90039
- Application / Permit
- 18014-10000-05881
- Plan Check / Job No.
- B18LA22031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Major alteration to existing garage: Convert the exising detached garage into a 2-story accessory dwelling unit with roof deck and attached 1-car garage per AB 494 and SB 229.
- Permit Issued
- Issued on 8/7/2020
- Issuing Office
- Current Status
- CofO Issued on 11/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2018 | APPLICANT |
| Green Plans Picked Up | 10/22/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2018 | ALBERT SERVIN |
| Corrections Issued | 10/29/2018 | ALBERT SERVIN |
| Quality Review Completed | 11/2/2018 | GARO TELMI |
| Applicant returned to address corrections | 1/11/2019 | ALBERT SERVIN |
| Applicant returned to address corrections | 1/25/2019 | ALBERT SERVIN |
| Plan Check Approved | 3/20/2019 | ALBERT SERVIN |
| Issued | 8/7/2020 | APPLICANT |
| Building Plans Picked Up | 8/13/2020 | APPLICANT |
| CofO in Progress | 10/21/2022 | THOMAS LOGRASSO |
| Permit Finaled | 11/6/2022 | DEROLD HAUFF |
| CofO Issued | 11/6/2022 | DEROLD HAUFF |
| Permit Finaled | 11/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/6/2018 | KARAN PATEL |
| Street width determination | Cleared | 11/6/2018 | KARAN PATEL |
| Supp. Use District POD/CDO/TDO | Cleared | 11/6/2018 | DIANA JIMENEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2018 | CELINA MORENO |
| Sewer availability | Cleared | 12/5/2018 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/14/2018 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/4/2019 | RYAN HUDSON |
| Construction near power lines | Cleared | 2/15/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/15/2019 | RIDWAN HARDY |
| Green Code | Cleared | 3/14/2019 | KHEDER ALRAZAA |
Contact Information
| Contractor | D C L A Design Build Inc; Lic. No.: 1060451-B | 712 N BONNIE BRAE ST LOS ANGELES, CA 90026 |
| Engineer | Refugio, Dominguez; Lic. No.: C50820 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/4/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/12/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/3/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 12/27/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/4/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 1/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 1/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 1/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 1/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/18/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/18/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 2/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 2/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 3/18/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/18/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 3/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 3/22/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/22/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/23/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 4/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 4/15/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/16/2022 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/16/2022 | Partial Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 8/16/2022 | Partial Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 8/16/2022 | Partial Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 9/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 9/30/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 9/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 9/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 9/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 10/13/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 10/13/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 10/13/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 10/13/2022 | Approved | THOMAS LOGRASSO |
| Final | 10/19/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 10/19/2022 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 10/19/2022 | Approved | THOMAS LOGRASSO |
| Final | 10/21/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 10/21/2022 | Approved | THOMAS LOGRASSO |