9121 W ALTO CEDRO DR 90210

Certificate Information: 9121 W ALTO CEDRO DR 90210

Application / Permit
18014-10000-05826
Plan Check / Job No.
B18LA21832
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION AND ALTERATION TO SINGLE FAMILY DWELLING TO REMODEL ENTRANCE AND ADD DECK ***"COMPLY WITH DEPARTMENT ORDER effective date 11/08/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/6/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2018 APPLICANT
Assigned to Plan Check Engineer 10/25/2018 SINA KHOSRAVI
Corrections Issued 10/31/2018 SINA KHOSRAVI
Quality Review Completed 11/2/2018 DAVID CHANG
Building Plans Picked Up 11/8/2018 APPLICANT
Applicant returned to address corrections 2/13/2019 SINA KHOSRAVI
Applicant returned to address corrections 2/26/2019 SINA KHOSRAVI
Plan Check Approved 3/6/2019 SINA KHOSRAVI
Issued 3/6/2019 LADBS
CofO in Progress 5/18/2021 JOEL WILLIAMS
CofO Issued 6/10/2021 DANIEL SANCHEZ
Permit Finaled 6/10/2021 DANIEL SANCHEZ

Permit Application Clearance Information

Specific Plan Cleared 2/5/2019 DOMINICK ORTIZ
Grading Pre-Inspection Cleared 3/6/2019 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C43008       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2019 Not Ready for Inspection GORDON ZUBER
Footing/Foundation/Slab 11/19/2019 Approved GORDON ZUBER
Deputy Drilled-In Anchors 9/25/2020 No Result Entered TIMOTHY KEY
ELECTRICAL-Rough 11/17/2020 Approved GORDON ZUBER
HVAC-Rough 11/17/2020 Approved GORDON ZUBER
PLUMBING-Rough 11/17/2020 Approved GORDON ZUBER
Deputy Steel/Welding 11/18/2020 Partial Approval JOEL WILLIAMS
Insulation 11/23/2020 Approved GORDON ZUBER
Drywall Nailing 11/30/2020 Approved GORDON ZUBER
Interior/Exterior Lathing 1/26/2021 Approved GORDON ZUBER
BUILDING-Rough-Frame 4/22/2021 Approved GORDON ZUBER
Final 4/22/2021 OK to Issue CofO GORDON ZUBER
Green Building Final 4/22/2021 Approved GORDON ZUBER
Green Building Rough 4/22/2021 Approved GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Approved GORDON ZUBER
Smoke Detectors 4/22/2021 Approved GORDON ZUBER