Deputy Reinf. Concrete
|
6/3/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/3/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/3/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/6/2020
|
Approved
|
DARRYL ARNOLD
|
|
Footing/Foundation/Slab
|
6/6/2020
|
Off-Hour Fees Due
|
|
|
Deputy Reinf. Concrete
|
6/8/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/18/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/19/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/22/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/23/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/26/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2020
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/30/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/2/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/13/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/15/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/16/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/17/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/27/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/4/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/5/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
8/5/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/5/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/7/2020
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Masonry
|
8/10/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
8/11/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/12/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/12/2020
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/13/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/14/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
8/17/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/18/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
8/19/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/21/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/27/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
8/27/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
8/28/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/29/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/14/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
10/14/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/5/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/6/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/9/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
11/10/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/13/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
11/17/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Excavation/Setback/Form/Re-Bar
|
11/18/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/19/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
11/20/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/2/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/3/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
12/4/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/7/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
12/8/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
12/8/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/16/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
12/22/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
12/23/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
12/24/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
12/24/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
12/29/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
12/30/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
12/31/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
1/4/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
1/6/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
1/7/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/20/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/22/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/25/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
1/28/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/1/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/5/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Wood Frame
|
2/23/2021
|
Partial Approval
|
TIMOTHY BUXTON
|
|
Deputy Drilled-In Anchors
|
2/25/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/2/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
3/26/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
3/30/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/31/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
4/7/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
4/7/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
4/8/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Steel/Welding
|
4/9/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
4/13/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
4/14/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Steel/Welding
|
4/16/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Steel/Welding
|
4/30/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/12/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/18/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/3/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Wood Construction
|
7/8/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Wood Frame
|
7/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
7/15/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Insulation
|
7/23/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
8/12/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Interior/Exterior Lathing
|
8/27/2021
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Interior/Exterior Lathing
|
9/3/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
9/22/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
T-Bar Ceiling
|
9/22/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
9/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Pre-Inspection
|
11/9/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Pre-Inspection
|
12/6/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Final
|
9/23/2022
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
9/23/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
9/23/2022
|
Approved
|
GREGORY POMISH
|
|
Reinforced Masonry Frame
|
9/23/2022
|
Approved
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
9/23/2022
|
SGSOV Approved
|
GREGORY POMISH
|
|
Smoke Detectors
|
9/23/2022
|
Approved
|
GREGORY POMISH
|
|
Final
|
12/12/2022
|
OK to Issue CofO
|
GREGORY POMISH
|
|
Green Building Final
|
12/12/2022
|
Approved
|
GREGORY POMISH
|