3931-3933 S WELLAND AVE 90008

Certificate Information: 3931-3933 S WELLAND AVE 90008

Application / Permit
18014-10000-05794
Plan Check / Job No.
B18LA21685
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One and two story addition to rear of an (E) SFD with new covered porch. Remodel entire (E) SFD. Conversion of 2nd story to an Accessory Dwelling Unit per AB 494 and SB 229.
Permit Issued
Issued on 10/15/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2018 APPLICANT
Assigned to Plan Check Engineer 11/8/2018 HELEN NGUYEN
Green Plans Picked Up 11/8/2018 APPLICANT
Corrections Issued 11/26/2018 HELEN NGUYEN
Quality Review Completed 12/10/2018 BILL STUTSMAN
Building Plans Picked Up 12/10/2018 APPLICANT
Applicant returned to address corrections 2/26/2019 HELEN NGUYEN
Applicant returned to address corrections 9/13/2019 HELEN NGUYEN
Plan Check Approved 10/8/2019 HELEN NGUYEN
Issued 10/15/2019 LADBS
CofO in Progress 9/8/2021 DAVID FEILER
CofO Issued 10/2/2021 DEROLD HAUFF
Permit Finaled 10/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 2/13/2019 KHEDER ALRAZAA
Address approval Cleared 2/20/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 10/7/2019 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 10/8/2019 ROBYN STEELE
Roof/Waste drainage to street Cleared 10/8/2019 JEANETTE VONG
Sewer availability Cleared 10/8/2019 ROBYN STEELE

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2019 Partial Inspection COREY HUPP
Footing/Foundation/Slab 12/20/2019 Conditional Approval COREY HUPP
PLUMBING-Rough 1/29/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 2/3/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 2/6/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Partial Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Partial Approval COREY HUPP
ELECTRICAL-Rough 8/14/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 8/14/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 8/14/2020 Approved COREY HUPP
ELECTRICAL-Rough 8/21/2020 Approved JOSEPH MCGARRY
HVAC-Rough 8/21/2020 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 9/9/2020 Partial Approval DONALD CRICHLOW
Green Building Rough 9/9/2020 Corrections Issued DONALD CRICHLOW
HVAC-Rough 9/9/2020 Corrections Issued DONALD CRICHLOW
BUILDING-Rough-Frame 9/15/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 9/15/2020 Partial Approval COREY HUPP
HVAC-Rough 9/15/2020 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 10/7/2020 Approved DAVID FEILER
Green Building Rough 10/7/2020 Approved DAVID FEILER
HVAC-Rough 10/7/2020 Approved DAVID FEILER
Insulation 10/20/2020 Approved DAVID FEILER
Drywall Nailing 10/28/2020 Approved DAVID FEILER
Interior/Exterior Lathing 10/28/2020 Partial Approval DAVID FEILER
ELECTRICAL-Rough 12/4/2020 Not Ready for Inspection DAVID FEILER
Underground Mechanical 12/4/2020 Corrections Issued DAVID FEILER
Gas Test 12/21/2020 Partial Approval DAVID FEILER
Underground Mechanical 12/21/2020 Partial Approval DAVID FEILER
Shower Pan 2/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 2/4/2021 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 2/9/2021 No Access for Inspection DAVID FEILER
Shower Pan 2/12/2021 Corrections Issued DAVID FEILER
Shower Pan 2/22/2021 Approved DAVID FEILER
Final 7/1/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/1/2021 Approved FREDDIE RIVERA
Green Building Final 7/1/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 7/1/2021 Approved FREDDIE RIVERA
Final 7/30/2021 Partial Inspection DAVID FEILER
Green Building Final 7/30/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Not Ready DAVID FEILER
Final 8/18/2021 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Not Ready DAVID FEILER
Final 9/7/2021 OK to Issue CofO DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved DAVID FEILER
Service/Power Release 9/7/2021 Approved DAVID FEILER
Special/Order Compliance 9/7/2021 Partial Approval ASHLEY THOMPSON