5036 1/2 N LA RODA AVE 90041

Certificate Information: 5036 1/2 N LA RODA AVE 90041

Application / Permit
18014-10000-05484
Plan Check / Job No.
B18LA20574
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER AB494 AND SB229. AND ADD 4' X 15' LAUNDRY AND STORAGE ROOMS TO FRONT.
Permit Issued
Issued on 3/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 JESSE JIMENEZ
Corrections Issued 9/27/2018 JESSE JIMENEZ
Plan Check Approved 11/6/2019 MONICA RAMIREZ
Issued 3/26/2020 LADBS
CofO in Progress 2/23/2021 CRAIG VAUGHAN
Permit Finaled 3/6/2021 DEROLD HAUFF
CofO Issued 3/6/2021 DEROLD HAUFF
Permit Finaled 3/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/17/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 10/17/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 10/17/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/17/2019 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 10/18/2019 PATRICK MISCHLICH
Construction near power lines Cleared 10/26/2019 RIDWAN HARDY
Construction within easement Cleared 10/26/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Latifian, Amirmasoud; Lic. No.: C87552       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/22/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 7/22/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 7/22/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/22/2020 Partial Approval CRAIG VAUGHAN
Sewer 7/22/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/30/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/7/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/17/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/16/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/16/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Approved CRAIG VAUGHAN
Green Building Rough 9/16/2020 Approved CRAIG VAUGHAN
HVAC-Rough 9/16/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/16/2020 Approved CRAIG VAUGHAN
Insulation 9/22/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/22/2020 Approved CRAIG VAUGHAN
Drywall Nailing 9/28/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/13/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/18/2020 Corrections Issued CRAIG VAUGHAN
HVAC-Final 11/18/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 11/18/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/23/2020 Approved CRAIG VAUGHAN
Final 11/23/2020 Corrections Issued CRAIG VAUGHAN
Gas Test 11/23/2020 Approved CRAIG VAUGHAN
Green Building Final 11/23/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 11/23/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/23/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 11/23/2020 Approved CRAIG VAUGHAN
Final 2/22/2021 OK to Issue CofO CRAIG VAUGHAN