648 E FLORENCE AVE 90001
Certificate Information: 648 E FLORENCE AVE 90001
- Application / Permit
- 18014-10000-05222
- Plan Check / Job No.
- B18LA19503
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- REMODEL AND ADD 2ND STORY TO (E) ONE STORY OFFICE BUILDING AND RESTRIPE PARKING LOT
- Permit Issued
- Issued on 8/7/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2018 | YAQUB MIRZA |
| Disabled Access Plans Picked Up | 10/3/2018 | APPLICANT |
| Green Plans Picked Up | 10/3/2018 | APPLICANT |
| Corrections Issued | 10/10/2018 | YAQUB MIRZA |
| Quality Review Completed | 10/18/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/26/2018 | APPLICANT |
| Plan Check Approved | 7/31/2019 | YAQUB MIRZA |
| Issued | 8/7/2019 | LADBS |
| CofO in Progress | 8/15/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 8/15/2024 | RAFAEL ESPINOZA |
| CofO Issued | 8/15/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 8/15/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Green Code | Cleared | 5/2/2019 | SARAH ABOULHOSN |
| DAS Clearance | Cleared | 6/19/2019 | SHINE LIN |
| Low Impact Development | Cleared | 6/19/2019 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2019 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 6/20/2019 | ANNA VAN |
| Permit | Cleared | 6/20/2019 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/20/2019 | JEANIE LAM |
| Sewer availability | Cleared | 6/20/2019 | JEANIE LAM |
| Trees in Parkway | Cleared | 6/20/2019 | JOHN KIM |
| Comm Cor/Mini-Mall | Cleared | 7/16/2019 | SOPHIE GABEL-SCHEINBAU |
| Highway dedication | Cleared | 7/24/2019 | CELINA MORENO |
Contact Information
| Architect | Herrera,, Victor Javier; Lic. No.: C37003 | 9631 S. 4TH AVENUE INGLEWOOD, CA 90305 |
| Contractor | G W Construction; Lic. No.: 833648-B | 3770 OCEAN VIEW AVENUE LOS ANGELES, CA 90066 |
| Engineer | Hoballah,, Tarek Ali; Lic. No.: S4124 | 2600 E PACIFIC COAST HWY STE 170 LONG BEACH, CA 90804 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2019 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/5/2019 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/17/2019 | Conditional Approval | JOEY BUCHANAN |
| Special/Order Compliance | 11/7/2019 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 11/7/2019 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 3/3/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Wood Frame | 3/3/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Approved | LANNY MERRICK |
| Deputy Wood Construction | 6/17/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 8/6/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 8/6/2020 | Partial Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 9/17/2020 | Approved | LEOPOLDO MENDOZA |
| Masonry Wall/Backfill | 10/16/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 11/13/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Approved | LANNY MERRICK |
| Wall Anchors | 2/22/2021 | Approved | LANNY MERRICK |
| Wood Frame | 2/22/2021 | Approved | LANNY MERRICK |
| Insulation | 4/15/2021 | Approved | LANNY MERRICK |
| Drywall Nailing | 4/28/2021 | Approved | LANNY MERRICK |
| Deputy Drilled-In Anchors | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Wood Construction | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Insulation | 8/9/2023 | Approved | ALAN MORELOS |
| Drywall Nailing | 8/18/2023 | Approved | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 10/18/2023 | Approved | DARRYL ARNOLD |
| Final | 5/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Green Building Final | 5/21/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 5/21/2024 | Approved | ALFREDO LOPEZ |
| Final | 7/23/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/15/2024 | OK to Issue CofO | RAFAEL ESPINOZA |