10000 N ORION AVE 91345
Certificate Information: 10000 N ORION AVE 91345
- Application / Permit
- 18014-10000-05170
- Plan Check / Job No.
- B18LA19301
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 1430 SF TO (E) SINGLE FAMILY RESIDENCE; AREA OF ADDITION INCLUDES A NEW ENTRY, KITCHEN, MASTER BEDROOM, MASTER BATH, CLOSET, LIVING ROOM, LAUNDRY
- Permit Issued
- Issued on 12/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2018 | ANA AVELAR |
| Corrections Issued | 10/11/2018 | ANA AVELAR |
| Quality Review Completed | 10/16/2018 | KESETE HAREGOT |
| Green Plans Picked Up | 10/24/2018 | APPLICANT |
| Plan Check Approved | 11/19/2018 | ANA AVELAR |
| Issued | 12/6/2018 | LADBS |
| Building Plans Picked Up | 10/19/2021 | APPLICANT |
| CofO in Progress | 8/30/2022 | JENNIFER RABUCHIN |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/8/2018 | ROBERT DUFF |
| Green Code | Cleared | 11/9/2018 | ANA AVELAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2018 | JEANETTE VONG |
| Low Impact Development | Cleared | 11/19/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/19/2018 | JEANETTE VONG |
| Sewer availability | Cleared | 11/19/2018 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C71428 | 5410 WEST 190TH STREET UNIT 65 TORRANCE, CA 90503 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2019 | Conditional Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/19/2019 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/8/2019 | Partial Approval | JENNIFER RABUCHIN |
| Service/Power Release | 7/3/2019 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 7/10/2019 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/19/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/5/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/5/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/5/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 2/5/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 2/5/2021 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/4/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 3/4/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/4/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/25/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 10/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/25/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/25/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 10/25/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/28/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/28/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/28/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/28/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/2/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/4/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 11/4/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 5/19/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| Final | 5/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/31/2022 | OK to Issue CofO | JENNIFER RABUCHIN |