19260 W NORDHOFF ST 91324

Certificate Information: 19260 W NORDHOFF ST 91324

Application / Permit
18014-10000-04989
Plan Check / Job No.
B18LA18583
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(9) Car Wash
Work Description
NEW CARWASH 1,040 ADDITION TO EXISTING GAS STATION
Permit Issued
Issued on 2/26/2020
Issuing Office
Valley
Current Status
CofO in Progress on 5/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 CHON CHIO KUO
Corrections Issued 9/24/2018 CHON CHIO KUO
Disabled Access Plans Picked Up 9/24/2018 APPLICANT
Quality Review Completed 9/25/2018 STEVEN KIM
Building Plans Picked Up 10/3/2018 APPLICANT
Green Plans Picked Up 10/11/2018 APPLICANT
Applicant returned to address corrections 3/12/2019 CHON CHIO KUO
Applicant returned to address corrections 3/18/2019 CHON CHIO KUO
Applicant returned to address corrections 9/20/2019 CHON CHIO KUO
Applicant returned to address corrections 1/22/2020 CHON CHIO KUO
Plan Check Approved 2/7/2020 CHON CHIO KUO
Issued 2/26/2020 LADBS
CofO in Progress 5/16/2023 JEFFREY FULTON
CofO in Progress 3/7/2024 GREGORY POMISH

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/11/2018 ROBERT DUFF
ZA Case Cleared 3/13/2019 TREVOR MARTIN
ZA Case Cleared 3/13/2019 TREVOR MARTIN
DAS Clearance Cleared 4/3/2019 CHON CHIO KUO
Driveway location Cleared 4/24/2019 COLLINS ALLAN
Eng Process Fee Ord 176,300 Cleared 4/24/2019 ELAINE LEI
Highway dedication Cleared 5/15/2019 ISRAEL TAMIRU
Low Impact Development Cleared 5/15/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 5/15/2019 ISRAEL TAMIRU
Stormwater Pollution Mitigatn Cleared 5/15/2019 MITESH PATEL
Sewer availability Cleared 5/21/2019 JEANIE LAM
Supplemental Onsite WTS Cleared 5/21/2019 KENNETH BROWNE
Green Code Cleared 8/14/2019 SARAH ABOULHOSN
"Q" conditions Cleared 1/7/2020 SOPHIE GABEL-SCHEINBAU
"T" removal Cleared 1/7/2020 SOPHIE GABEL-SCHEINBAU
APC Cleared 1/7/2020 SOPHIE GABEL-SCHEINBAU
Prkng lot landscape/Water mgmt Cleared 1/7/2020 SOPHIE GABEL-SCHEINBAU

Contact Information

Contractor Superior Construction; Lic. No.: 852082-B 16018 CIRCLE DIAMOND ROAD      SYLMAR, CA 91342
Engineer Bradley,, John Forsyth; Lic. No.: S4486 9516 LOS PALOS ROAD      ATASCADERO, CA 93422
Engineer Fiedler,, Patrick O'Neill; Lic. No.: C38123 299 N EUCLID AVE SUITE 550      PASADENA, CA 91101

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2020 No Access for Inspection JEFFREY FULTON
Pre-Inspection 8/24/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/30/2021 Approved KENNETH ROBERTS
Deputy Reinf. Concrete 10/1/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/13/2021 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Not Ready for Inspection JEFFREY FULTON
Insulation 10/18/2021 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/20/2021 Corrections Issued JEFFREY FULTON
Insulation 10/21/2021 Not Ready for Inspection JEFFREY FULTON
Insulation 10/22/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/3/2021 Partial Inspection JEFFREY FULTON
Insulation 11/3/2021 Approved JEFFREY FULTON
Insulation 11/4/2021 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/5/2021 Approved KENNETH ROBERTS
Drywall Nailing 11/8/2021 Approved JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 2/2/2022 Partial Inspection JEFFREY FULTON
Final 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Final 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 8/22/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Structural Steel Frame 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Final 10/18/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Final 10/18/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 10/18/2022 Approved JEFFREY FULTON
Reinforced Masonry Frame 10/18/2022 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 10/18/2022 Approved JEFFREY FULTON
Structural Steel Frame 10/18/2022 Approved JEFFREY FULTON
Pre-Inspection 11/7/2022 Partial Inspection DANIEL VARNUM
Final 11/8/2022 Corrections Issued JEFFREY FULTON
Green Building Final 11/8/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready JEFFREY FULTON
Special/Order Compliance 11/8/2022 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 11/21/2022 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/21/2022 Corrections Issued JEFFREY FULTON
Final 4/26/2023 OK to Issue CofO JEFFREY FULTON
Green Building Final 4/26/2023 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Approved JEFFREY FULTON