1517 W 97TH ST 90047

Certificate Information: 1517 W 97TH ST 90047

Application / Permit
18014-10000-04887
Plan Check / Job No.
B18LA18080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY 34'-6"X21'-6" IRREGULAR ADDITION TO EXISTING DETACHED GARAGE FOR ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 2/25/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2018 APPLICANT
Assigned to Plan Check Engineer 9/27/2018 GEORGE ALVAREZ
Green Plans Picked Up 10/3/2018 APPLICANT
Corrections Issued 10/16/2018 GEORGE ALVAREZ
Quality Review Completed 10/23/2018 MICHAEL PEREZ
Building Plans Picked Up 10/26/2018 APPLICANT
Plan Check Approved 8/6/2019 GEORGE ALVAREZ
Issued 2/25/2020 LADBS
CofO in Progress 10/1/2021 FREDDIE RIVERA
Permit Finaled 10/13/2021 DEROLD HAUFF
CofO Issued 10/13/2021 DEROLD HAUFF
Permit Finaled 10/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 5/13/2019 SARAH ABOULHOSN
CPC Cleared 6/5/2019 ANNA VAN
Address approval Cleared 7/15/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/15/2019 ROBYN STEELE
Hydrant and Access approval Cleared 7/15/2019 GILBERT URREA
Low Impact Development Cleared 7/15/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/15/2019 ERIK BEASLEY
Sewer availability Cleared 7/15/2019 ROBYN STEELE
Street width determination Cleared 7/15/2019 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Pezeshkian, Vahik; Lic. No.: C35278 1545 N VERDUGO RD 217      GLENDALE, CA 91208

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/10/2020 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 8/10/2020 Not Ready for Inspection FREDDIE RIVERA
METHANE-Barrier 8/10/2020 Not Ready for Inspection FREDDIE RIVERA
METHANE-Subgrade 8/10/2020 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 11/16/2020 Corrections Issued FREDDIE RIVERA
METHANE-Barrier 11/16/2020 Approved FREDDIE RIVERA
METHANE-Subgrade 11/16/2020 Approved FREDDIE RIVERA
Footing/Foundation/Slab 11/20/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 12/17/2020 Approved FREDDIE RIVERA
Sewer 12/17/2020 Approved FREDDIE RIVERA
Wood Frame 12/17/2020 Partial Approval FREDDIE RIVERA
Special/Order Compliance 2/10/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/16/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/16/2021 Approved FREDDIE RIVERA
Green Building Rough 2/16/2021 Approved FREDDIE RIVERA
HVAC-Rough 2/16/2021 Approved FREDDIE RIVERA
METHANE-Rough 2/16/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 2/16/2021 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 2/18/2021 Approved EUGENE CASSIDY
HVAC-Rough 2/18/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 2/18/2021 Corrections Issued EUGENE CASSIDY
Special/Order Compliance 2/18/2021 Corrections Issued EUGENE CASSIDY
Wood Frame 2/18/2021 Approved EUGENE CASSIDY
Insulation 3/1/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/1/2021 Partial Approval FREDDIE RIVERA
Drywall Nailing 3/10/2021 Approved FREDDIE RIVERA
Final 5/26/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 5/26/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 5/26/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 6/14/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 7/12/2021 Approved FREDDIE RIVERA
Final 8/25/2021 OK to Issue CofO FREDDIE RIVERA
Green Building Final 8/25/2021 Approved FREDDIE RIVERA
Smoke Detectors 8/25/2021 Approved FREDDIE RIVERA