19364 W KITTRIDGE ST 91335

Certificate Information: 19364 W KITTRIDGE ST 91335

Application / Permit
18014-10000-04873
Plan Check / Job No.
B18LA18037
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to existing single family dwelling
Permit Issued
Issued on 6/10/2020
Issuing Office
Metro
Current Status
Issued on 6/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/24/2018 SHANGQIN XIE
Corrections Issued 8/24/2018 SHANGQIN XIE
Plan Check Approved 5/30/2019 JAMES DETCHMENDY
Issued 6/10/2020 LADBS

Permit Application Clearance Information

Low Impact Development Cleared 5/22/2019 RYAN HUDSON
ZI Cleared 5/22/2019 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 5/30/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 5/30/2019 ELENA LOPEZ

Contact Information

No Data Available.

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/22/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/9/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Approved VINCENT HANLEY
HVAC-Rough 12/9/2020 Approved VINCENT HANLEY
PLUMBING-Rough 12/9/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 1/5/2021 Partial Approval VINCENT HANLEY
Green Building Rough 1/5/2021 Approved VINCENT HANLEY
Insulation 1/5/2021 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 1/5/2021 Approved VINCENT HANLEY
Drywall Nailing 1/20/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/15/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 6/15/2021 Corrections Issued VINCENT HANLEY
Final 6/15/2021 Not Ready for Inspection VINCENT HANLEY
Gas Test 6/15/2021 Approved VINCENT HANLEY
HVAC-Final 6/15/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 6/15/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 6/15/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/16/2021 Approved VINCENT HANLEY
Green Building Final 6/16/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 6/16/2021 Approved VINCENT HANLEY