5011 W NOVGOROD ST 90032

Certificate Information: 5011 W NOVGOROD ST 90032

Application / Permit
18014-10000-04744
Plan Check / Job No.
B18LA17435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition to 1-story SFD. Add bedroom/bathroom on west side. Add 2-car garage on the east side. Remove attached carport.
Permit Issued
Issued on 10/21/2019
Issuing Office
Metro
Current Status
Issued on 10/21/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2018 APPLICANT
Assigned to Plan Check Engineer 8/20/2018 SINA KHOSRAVI
Corrections Issued 8/20/2018 SINA KHOSRAVI
Applicant returned to address corrections 3/13/2019 SAM CHANG
Applicant returned to address corrections 3/27/2019 DEVIN GORDON
Applicant returned to address corrections 4/9/2019 ARSALAN SHABESTARI
Plan Check Approved 10/21/2019 KEVIN MORALES
Issued 10/21/2019 LADBS

Permit Application Clearance Information

Low Impact Development Cleared 1/9/2019 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 2/13/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 2/13/2019 ADRIAN SANCHEZ
Sewer availability Cleared 2/26/2019 ELENA LOPEZ
Grading Pre-Inspection Cleared 3/1/2019 PATRICK MISCHLICH
"D" conditions Cleared 3/12/2019 SANTOS SANCHEZ
"Q" conditions Cleared 3/12/2019 SANTOS SANCHEZ
GPI Written Notices Cleared 4/9/2019 SINA KHOSRAVI
Construction near power lines Cleared 10/17/2019 RIDWAN HARDY

Contact Information

Contractor J P Construction; Lic. No.: 977312-B 27910 VIADELA REAL      MORENO VALLEY, CA 92555
Engineer Moreno,, Hector M; Lic. No.: C66015 1430 E COOLEY DR SUITE 120      COLTON, CA 92324

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/7/2019 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/14/2019 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/5/2019 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 12/5/2019 Partial Approval RUBEN SALAS
Green Building Rough 12/5/2019 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 2/12/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 2/12/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/12/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 3/2/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 3/2/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 3/2/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 3/2/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 3/19/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/19/2020 Approved ENRIQUE MIRELES
Green Building Rough 3/19/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/19/2020 Approved ENRIQUE MIRELES
Insulation 3/24/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 3/24/2020 Approved THOMAS LOGRASSO
Drywall Nailing 3/27/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 3/27/2020 Approved THOMAS LOGRASSO
Final 5/8/2020 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/8/2020 Approved ENRIQUE MIRELES
Green Building Final 5/8/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 5/8/2020 Approved ENRIQUE MIRELES
Smoke Detectors 5/8/2020 Approved ENRIQUE MIRELES
Final 6/30/2020 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV Approved ENRIQUE MIRELES