19613 W HAYNES ST 91335

Certificate Information: 19613 W HAYNES ST 91335

Application / Permit
18014-10000-04689
Plan Check / Job No.
B18LA17252
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 3/21/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2018 APPLICANT
Assigned to Plan Check Engineer 8/20/2018 MICHAEL LOPEZ
Corrections Issued 8/20/2018 MICHAEL LOPEZ
Plan Check Approved 3/21/2019 SHANGQIN XIE
Issued 3/21/2019 LADBS
CofO in Progress 6/8/2020 HENRY KIM
Permit Finaled 6/10/2020 JOHN JANSON
CofO Issued 6/10/2020 JOHN JANSON
Permit Finaled 6/10/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/20/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 8/20/2018 MICHAEL CASTILLO
Roof/Waste drainage to street Cleared 8/20/2018 MICHAEL CASTILLO
Sewer availability Cleared 8/20/2018 MICHAEL CASTILLO
ZI Cleared 8/20/2018 IVORY CHAMBESHI
Construction near power lines Cleared 2/11/2019 RIDWAN HARDY
Construction within easement Cleared 2/11/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2019 Partial Approval JOHN COLEMAN
Underground Mechanical 5/7/2019 Approved JOHN COLEMAN
Footing/Foundation/Slab 5/10/2019 Approved JOHN COLEMAN
BUILDING-Rough-Frame 7/24/2019 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 7/24/2019 Approved JOHN COLEMAN
Green Building Rough 7/24/2019 Approved JOHN COLEMAN
HVAC-Rough 7/24/2019 Partial Inspection JOHN COLEMAN
PLUMBING-Rough 7/24/2019 Approved JOHN COLEMAN
BUILDING-Rough-Frame 8/8/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 9/3/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 9/19/2019 Approved JOHN COLEMAN
HVAC-Rough 9/19/2019 Approved JOHN COLEMAN
Insulation 9/24/2019 Approved DAVID SANDOVAL
Shower Pan 9/24/2019 Not Ready for Inspection DAVID SANDOVAL
Drywall Nailing 10/7/2019 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 10/7/2019 Corrections Issued DAVID SANDOVAL
Shower Pan 10/7/2019 Not Ready for Inspection DAVID SANDOVAL
Drywall Nailing 10/11/2019 Approved DAVID SCANTLIN
ELECTRICAL-Final 5/21/2020 Corrections Issued HENRY KIM
Final 5/21/2020 Corrections Issued HENRY KIM
HVAC-Final 5/21/2020 Corrections Issued HENRY KIM
Interior/Exterior Lathing 5/21/2020 Corrections Issued HENRY KIM
PLUMBING-Final 5/21/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/21/2020 SGSOV Not Ready HENRY KIM
Service/Power Release 5/21/2020 Not Ready for Inspection HENRY KIM
Shower Pan 5/21/2020 Approved HENRY KIM
Smoke Detectors 5/21/2020 Approved HENRY KIM
ELECTRICAL-Final 6/2/2020 Corrections Issued HENRY KIM
Final 6/2/2020 Not Ready for Inspection HENRY KIM
Green Building Final 6/2/2020 Approved HENRY KIM
HVAC-Final 6/2/2020 Approved HENRY KIM
Interior/Exterior Lathing 6/2/2020 Approved HENRY KIM
PLUMBING-Final 6/2/2020 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 6/2/2020 SGSOV Not Ready HENRY KIM
ELECTRICAL-Final 6/8/2020 Approved HENRY KIM
Final 6/8/2020 OK to Issue CofO HENRY KIM
PLUMBING-Final 6/8/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Approved HENRY KIM