6009 N OAKDALE AVE 91367
Certificate Information: 6009 N OAKDALE AVE 91367
- Application / Permit
- 18014-10000-04562
- Plan Check / Job No.
- B18LA16730
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MAJOR REMODEL AND ADDITION TO (E) SFD AND 2-CAR GARAGE TO ADD MASTER BEDROOM, POWDER ROOM AND ENLARGE GARAGE TO 4-CAR
- Permit Issued
- Issued on 2/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2018 | SINA KHOSRAVI |
| Corrections Issued | 8/10/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/4/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/14/2019 | ARSALAN SHABESTARI |
| Issued | 2/21/2019 | LADBS |
| CofO in Progress | 4/27/2021 | STEVEN BACK |
| Permit Finaled | 5/13/2021 | JOHN JANSON |
| CofO Issued | 5/13/2021 | JOHN JANSON |
| Permit Finaled | 5/13/2021 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/27/2018 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2018 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/31/2018 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 12/31/2018 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/26/2019 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 2/27/2019 | Corrections Issued | JOHN JANSON |
| Footing/Foundation/Slab | 3/19/2019 | Not Ready for Inspection | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 3/22/2019 | Corrections Issued | JOHN JANSON |
| Excavation/Setback/Form/Re-Bar | 4/5/2019 | Corrections Issued | JOHN JANSON |
| Deputy Drilled-In Anchors | 4/8/2019 | Conditional Approval | JOHN JANSON |
| Footing/Foundation/Slab | 4/9/2019 | Partial Approval | JOHN JANSON |
| BUILDING-Rough-Frame | 7/9/2019 | Partial Approval | SEAN WIRCH |
| Green Building Rough | 7/9/2019 | Not Ready for Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 10/18/2019 | Partial Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2020 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 2/6/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 2/6/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 2/12/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 2/12/2020 | Approved | STEVEN BACK |
| Deputy Wood Construction | 2/14/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 2/18/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 2/25/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 2/25/2020 | Approved | STEVEN BACK |
| Green Building Rough | 3/2/2020 | Approved | STEVEN BACK |
| Insulation | 3/2/2020 | Approved | STEVEN BACK |
| Shower Pan | 3/2/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/16/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/5/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/15/2020 | Approved | STEVEN BACK |
| HVAC-Final | 7/15/2020 | Corrections Issued | STEVEN BACK |
| Gas Test | 9/21/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 1/21/2021 | Approved | VINCENT HANLEY |
| Final | 1/21/2021 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/21/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 1/21/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/21/2021 | Approved | VINCENT HANLEY |
| Final | 1/28/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 3/8/2021 | Corrections Issued | STEVEN BACK |
| Final | 4/23/2021 | No Access for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 4/27/2021 | Approved | STEVEN BACK |
| Final | 4/27/2021 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 4/27/2021 | Approved | STEVEN BACK |
| PLUMBING-Final | 4/27/2021 | Approved | STEVEN BACK |
| Service/Power Release | 4/27/2021 | Approved | STEVEN BACK |