6009 N OAKDALE AVE 91367

Certificate Information: 6009 N OAKDALE AVE 91367

Application / Permit
18014-10000-04562
Plan Check / Job No.
B18LA16730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MAJOR REMODEL AND ADDITION TO (E) SFD AND 2-CAR GARAGE TO ADD MASTER BEDROOM, POWDER ROOM AND ENLARGE GARAGE TO 4-CAR
Permit Issued
Issued on 2/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2018 APPLICANT
Assigned to Plan Check Engineer 8/10/2018 SINA KHOSRAVI
Corrections Issued 8/10/2018 SINA KHOSRAVI
Applicant returned to address corrections 1/4/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 1/14/2019 ARSALAN SHABESTARI
Issued 2/21/2019 LADBS
CofO in Progress 4/27/2021 STEVEN BACK
Permit Finaled 5/13/2021 JOHN JANSON
CofO Issued 5/13/2021 JOHN JANSON
Permit Finaled 5/13/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/27/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/31/2018 JEANETTE VONG
Low Impact Development Cleared 12/31/2018 MARTIN FRAGOSO
Sewer availability Cleared 12/31/2018 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/26/2019 Approved SEAN WIRCH
Footing/Foundation/Slab 2/27/2019 Corrections Issued JOHN JANSON
Footing/Foundation/Slab 3/19/2019 Not Ready for Inspection SEAN WIRCH
Excavation/Setback/Form/Re-Bar 3/22/2019 Corrections Issued JOHN JANSON
Excavation/Setback/Form/Re-Bar 4/5/2019 Corrections Issued JOHN JANSON
Deputy Drilled-In Anchors 4/8/2019 Conditional Approval JOHN JANSON
Footing/Foundation/Slab 4/9/2019 Partial Approval JOHN JANSON
BUILDING-Rough-Frame 7/9/2019 Partial Approval SEAN WIRCH
Green Building Rough 7/9/2019 Not Ready for Inspection SEAN WIRCH
Footing/Foundation/Slab 10/18/2019 Partial Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/15/2020 Partial Approval STEVEN BACK
ELECTRICAL-Rough 2/6/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Not Ready for Inspection STEVEN BACK
HVAC-Rough 2/6/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 2/12/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Corrections Issued STEVEN BACK
HVAC-Rough 2/12/2020 Approved STEVEN BACK
Deputy Wood Construction 2/14/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Approved STEVEN BACK
PLUMBING-Rough 2/18/2020 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 2/25/2020 Approved STEVEN BACK
PLUMBING-Rough 2/25/2020 Approved STEVEN BACK
Green Building Rough 3/2/2020 Approved STEVEN BACK
Insulation 3/2/2020 Approved STEVEN BACK
Shower Pan 3/2/2020 Approved STEVEN BACK
Interior/Exterior Lathing 3/16/2020 Approved STEVEN BACK
PLUMBING-Rough 6/5/2020 Approved STEVEN BACK
ELECTRICAL-Rough 7/15/2020 Approved STEVEN BACK
HVAC-Final 7/15/2020 Corrections Issued STEVEN BACK
Gas Test 9/21/2020 Approved STEVEN BACK
Drywall Nailing 1/21/2021 Approved VINCENT HANLEY
Final 1/21/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 1/21/2021 Approved VINCENT HANLEY
Green Building Final 1/21/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/21/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/21/2021 Approved VINCENT HANLEY
Final 1/28/2021 Not Ready for Inspection VINCENT HANLEY
Final 3/8/2021 Corrections Issued STEVEN BACK
Final 4/23/2021 No Access for Inspection STEVEN BACK
ELECTRICAL-Final 4/27/2021 Approved STEVEN BACK
Final 4/27/2021 OK to Issue CofO STEVEN BACK
HVAC-Final 4/27/2021 Approved STEVEN BACK
PLUMBING-Final 4/27/2021 Approved STEVEN BACK
Service/Power Release 4/27/2021 Approved STEVEN BACK