8716 S CENTRAL AVE 90002
Certificate Information: 8716 S CENTRAL AVE 90002
- Application / Permit
- 18014-10000-04516
- Plan Check / Job No.
- B18LA16537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- Change of use from dental office to Child Care Center. and additon to rear of building and interior t.i., children (1-5 years).
- Permit Issued
- Issued on 9/2/2021
- Issuing Office
- Current Status
- CofO Corrected on 6/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | SAM CHANG |
| Corrections Issued | 9/11/2018 | SAM CHANG |
| Quality Review Completed | 9/13/2018 | SIAVOSH POURSABAHIAN |
| Disabled Access Plans Picked Up | 9/14/2018 | APPLICANT |
| Green Plans Picked Up | 11/2/2018 | APPLICANT |
| Applicant returned to address corrections | 1/23/2019 | SAM CHANG |
| Applicant returned to address corrections | 5/29/2020 | SAM CHANG |
| Applicant returned to address corrections | 7/14/2020 | SAM CHANG |
| Applicant returned to address corrections | 9/4/2020 | SAM CHANG |
| Plan Check Approved | 7/27/2021 | SAM CHANG |
| Issued | 9/2/2021 | APPLICANT |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| CofO in Progress | 8/4/2023 | ALAN MORELOS |
| CofO Issued-Status Void | 8/4/2023 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 8/4/2023 | ERNESTO CORRAL |
| Re-Activate Permit | 8/15/2023 | ERNESTO CORRAL |
| Permit Finaled | 6/28/2024 | ERNESTO CORRAL |
| CofO Corrected | 6/28/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/28/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 9/24/2018 | YOVANA PEREZ |
| CPC | Cleared | 9/24/2018 | YOVANA PEREZ |
| ZI | Cleared | 9/24/2018 | YOVANA PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/16/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 10/16/2018 | STEVE MELGAR |
| DAS Clearance | Cleared | 9/11/2019 | ELIZABETH TOMS |
| Green Code | Cleared | 1/30/2020 | SAM CHANG |
| Fire Marshall Fire Life Safety | Cleared | 6/2/2021 | DOMINIQUE MEDINA |
| Food establishment approval | Cleared | 7/27/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Gpp Construction Service Inc; Lic. No.: 943478-B | 350 N GLENDALE BLVD LOS ANGELES, CA 90026 |
| Engineer | Quiaot, Florentino V; Lic. No.: C38659 | 412 W 231ST ST CARSON, CA 90745 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Special/Order Compliance | 2/15/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/9/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/16/2022 | Approved | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 4/29/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 4/29/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | RUSSELL BONVOULOIR |
| Insulation | 6/8/2022 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 6/8/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/23/2022 | Approved | JAMES POWERS |
| Pre-Inspection | 9/23/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 10/14/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 10/14/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 10/14/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 10/14/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 10/14/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 10/26/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 5/25/2023 | Not Ready for Inspection | ALAN MORELOS |
| Final | 8/4/2023 | OK to Issue CofO | ALAN MORELOS |