1028 S GRAMERCY PL 90019
Certificate Information: 1028 S GRAMERCY PL 90019
- Application / Permit
- 18014-10000-04359
- Plan Check / Job No.
- B18LA15913
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT ADDITION TO (E) GARAGE PER AB 494 AND SB 229.
- Permit Issued
- Issued on 3/6/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | KEVIN MORALES |
| Green Plans Picked Up | 8/30/2018 | APPLICANT |
| Corrections Issued | 9/6/2018 | KEVIN MORALES |
| Quality Review Completed | 9/6/2018 | DAVID CHANG |
| Plan Check Approved | 2/28/2019 | KEVIN MORALES |
| Issued | 3/6/2019 | LADBS |
| CofO in Progress | 3/7/2020 | ALEJANDRO DE ARTOLA |
| CofO Issued | 3/14/2020 | DEROLD HAUFF |
| Permit Finaled | 3/14/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/30/2019 | SARAH ABOULHOSN |
| Address approval | Cleared | 2/14/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 2/27/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/27/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 2/27/2019 | JEANETTE VONG |
| HPOZ | Cleared | 2/28/2019 | BRADLEY FURUYA |
Contact Information
| Engineer | Park, Juntae; Lic. No.: C65104 | 1444 HI POINT ST LOS ANGELES, CA 90035 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2019 | Not Ready for Inspection | AJA COLLAY |
| METHANE-Barrier | 3/22/2019 | Not Ready for Inspection | AJA COLLAY |
| METHANE-Subgrade | 3/22/2019 | Not Ready for Inspection | AJA COLLAY |
| Pre-Inspection | 3/26/2019 | Corrections Issued | DAVID CHAN |
| Deputy Drilled-In Anchors | 4/3/2019 | Conditional Approval | AJA COLLAY |
| Footing/Foundation/Slab | 4/4/2019 | Approved | AJA COLLAY |
| METHANE-Barrier | 4/4/2019 | Approved | AJA COLLAY |
| METHANE-Subgrade | 4/4/2019 | Approved | AJA COLLAY |
| Underground Mechanical | 4/4/2019 | Approved | AJA COLLAY |
| BUILDING-Rough-Frame | 6/7/2019 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/7/2019 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 6/7/2019 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Rough | 6/7/2019 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 6/7/2019 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/17/2019 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/17/2019 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 6/17/2019 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 6/17/2019 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/3/2019 | Not Ready for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 7/3/2019 | Corrections Issued | ELMER BLAND |
| Gas Test | 7/3/2019 | Corrections Issued | ELMER BLAND |
| Green Building Rough | 7/3/2019 | Not Ready for Inspection | ELMER BLAND |
| HVAC-Rough | 7/3/2019 | Corrections Issued | ELMER BLAND |
| PLUMBING-Rough | 7/3/2019 | Not Ready for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 7/9/2019 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 7/9/2019 | Corrections Issued | ELMER BLAND |
| ELECTRICAL-Rough | 7/9/2019 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 7/9/2019 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 7/9/2019 | Corrections Issued | SCOTT FINNILA |
| Special/Order Compliance | 7/9/2019 | Corrections Issued | ELMER BLAND |
| Deputy Drilled-In Anchors | 8/7/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 8/12/2019 | Conditional Approval | CHARLENE BUSTAMANTE |
| BUILDING-Rough-Frame | 8/19/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/19/2019 | Partial Approval | SCOTT FINNILA |
| Gas Test | 8/19/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 8/19/2019 | Approved | SCOTT FINNILA |
| HVAC-Rough | 8/19/2019 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 8/19/2019 | Partial Approval | SCOTT FINNILA |
| Insulation | 9/3/2019 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/3/2019 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/10/2019 | Approved | AJA COLLAY |
| HVAC-Rough | 9/10/2019 | Approved | AJA COLLAY |
| PLUMBING-Rough | 9/10/2019 | Approved | AJA COLLAY |
| Sewer | 12/13/2019 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 12/23/2019 | Conditional Approval | SCOTT FINNILA |
| Final | 12/23/2019 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 12/23/2019 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/23/2019 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Final | 12/23/2019 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2019 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 12/23/2019 | Corrections Issued | SCOTT FINNILA |
| Final | 12/27/2019 | Not Ready for Inspection | LUIS BARRALES |
| Smoke Detectors | 12/27/2019 | Not Ready for Inspection | LUIS BARRALES |
| Final | 1/23/2020 | Corrections Issued | DAVID CHAN |
| Smoke Detectors | 1/23/2020 | Partial Approval | DAVID CHAN |
| Final | 2/6/2020 | Not Ready for Inspection | RICHARD STEINBACH |
| Smoke Detectors | 2/6/2020 | Approved | RICHARD STEINBACH |
| Final | 2/18/2020 | OK to Issue CofO | ALEJANDRO DE ARTOLA |