6101 1/2 E DELPHI ST 90042

Certificate Information: 6101 1/2 E DELPHI ST 90042

Application / Permit
18014-10000-04340
Plan Check / Job No.
B18LA15791
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING 223 SF SINGLE STORY GARAGE CONVERSION TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 WITH 44 SF ADDITION (267 SF TOTAL).
Permit Issued
Issued on 9/5/2018
Issuing Office
Metro
Current Status
CofO Issued on 3/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2018 APPLICANT
Assigned to Plan Check Engineer 7/31/2018 DEVIN GORDON
Corrections Issued 7/31/2018 DEVIN GORDON
Applicant returned to address corrections 8/14/2018 PRANITA SHAH
Plan Check Approved 8/15/2018 MICHAEL LOPEZ
Issued 9/5/2018 LADBS
CofO in Progress 3/1/2021 CRAIG VAUGHAN
Permit Finaled 3/6/2021 DEROLD HAUFF
CofO Issued 3/6/2021 DEROLD HAUFF
Permit Finaled 3/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 8/14/2018 NAZILA NOORIFAR
Grading Pre-Inspection Cleared 8/14/2018 PATRICK MISCHLICH
Hydrant and Access approval Cleared 8/14/2018 GILBERT URREA
Roof/Waste drainage to street Cleared 8/14/2018 NAZILA NOORIFAR
Sewer availability Cleared 8/14/2018 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2018 Partial Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 3/1/2019 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 3/1/2019 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 3/4/2019 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/7/2019 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/20/2019 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/20/2019 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 3/20/2019 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/20/2019 Not Ready for Inspection CRAIG VAUGHAN
Sewer 3/20/2019 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 3/20/2019 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 3/20/2019 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/22/2019 Partial Approval CRAIG VAUGHAN
Gas Test 3/22/2019 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/22/2019 Approved CRAIG VAUGHAN
Sewer 3/22/2019 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/3/2019 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 4/3/2019 Approved OSVALDO PARAMO
Sewer 4/3/2019 Approved OSVALDO PARAMO
Wood Frame 4/3/2019 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/9/2019 Approved PIERRE VEGA
Shower Pan 4/9/2019 Approved PIERRE VEGA
Drywall Nailing 4/15/2019 Approved RUBEN SALAS
Interior/Exterior Lathing 4/15/2019 Approved RUBEN SALAS
Final 6/24/2019 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 9/30/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 9/30/2020 Approved CRAIG VAUGHAN
Final 9/30/2020 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/30/2020 Approved CRAIG VAUGHAN
Green Building Final 9/30/2020 Approved CRAIG VAUGHAN
HVAC-Final 9/30/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 9/30/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/30/2020 Approved CRAIG VAUGHAN